Next Article in Journal
Better Earlier than Longer: First-Mover Advantage in Social Commerce Product Information Competition
Next Article in Special Issue
The Problem of Lighting in Underground Domes, Vaults, and Tunnel-Like Structures of Antiquity; An Application to the Sustainability of Prominent Asian Heritage (India, Korea, China)
Previous Article in Journal
A Study on Green Economy Indicators and Modeling: Russian Context
Previous Article in Special Issue
A Comparative Study on Current Outdoor Lighting Policies in China and Korea: A Step toward a Sustainable Nighttime Environment
 
 
Font Type:
Arial Georgia Verdana
Font Size:
Aa Aa Aa
Line Spacing:
Column Width:
Background:
Article

Italian Road Tunnels: Economic and Environmental Effects of an On-Going Project to Reduce Lighting Consumption

1
Department of Civil, Construction and Environmental Engineering, Sapienza University of Rome, 00184 Rome, Italy
2
Operation e Territorial Coordination Management, Anas S.p.A., 00185 Rome, Italy
*
Author to whom correspondence should be addressed.
Sustainability 2019, 11(17), 4631; https://doi.org/10.3390/su11174631
Submission received: 3 August 2019 / Revised: 19 August 2019 / Accepted: 20 August 2019 / Published: 26 August 2019
(This article belongs to the Special Issue Lighting at the Frontiers of Sustainable Development)

Abstract

:
Tunnel lighting represents a major cost item for road managers, and particularly in Italy owing to its specific geomorphological and orographic features. In 2018, ANAS, the Italian government-owned road company launched an ambitious program to rehabilitate the lighting systems of more than 700 tunnel tubes across Italy. The Greenlight plan aims to reduce consumption and improve the management of lighting systems while minimizing the impact of works. Outdated high-pressure sodium (HPS) luminaries will be substituted with state-of-the-art light emitting diode (LED) luminaries without modifying the position and the number of the existing luminaires. The project involves an amount of 155 million euros and provides a total return over a less than seven-year period. The first phase of the project involves 147 tubes and is still on-going: 28 GWh (on average 55% of the current consumption) will be saved every year against a 30 million euro investment. More importantly, the economic benefits also have a direct impact on the environment for citizens and safety levels for road users—every year more than 17,000 t of CO2 eq. and 230 TJ from combustion of fossil fuels will be saved. The lighting quality of the artificial lighting inside the tunnel will be enhanced thanks to better uniformity and the color temperature of the luminaries. The experience presented here could be useful since other road managers may pursue a similar approach in order to balance often-conflicting environmental, economic and safety goals.

1. Introduction

According to the European Commission, improving energy efficiency is a broad term. Improvements in energy efficiency and energy saving are the two key targets [1]. An effective energy efficiency policy could contribute to EU competitiveness and encourage eco-innovation, on the other hand, energy saving is the first option for improving energy efficiency and is undoubtedly the quickest, most cost-effective way to reduce environmental impacts [2]. In the public sector, more efficient lighting can contribute to improving environmental sustainability of our lifestyle [3]. In 2009, 14% of the total electricity consumption in Europe was for lighting, and more than half of this was for public spaces and non-residential applications [4]. In particular, over 70% of existing light sources are based on obsolete technologies that have poor energy performance, and for which a better alternative is available [5].
Public lighting is 2% of the overall value [6] of energy consumption in Italy, however, both renewal of technologies and energy rationalization processes could contribute to meeting the three key targets set by EU on climate and energy (i.e., 20% cut in greenhouse gas emissions, 20% of EU from renewables, and 20% improvement in energy efficiency). Among the various and important functions of public lighting is ensuring safety for the movement of traffic and pedestrians. In order to ensure the minimum safety illumination values on roads, specific standards have been set to define minimum luminance and illuminance levels according to the area to be illuminated. In Europe, the updated standard CEN/TR 13201-1:2014 [7] on road lighting provides far greater potential for dynamic control then the previous standard CEN/TR 13201-1:2004 [8], which results in significant energy saving [9,10]. Lighting costs represent up to 25% of the total budget for management of the road network [11], therefore both energy performance indicators and environmental criteria should be adopted when designing smart public lighting systems [12,13]. In particular, safety measures for tunnels and their overall equipment involve a high-energy consumption [14]. The aim of tunnel lighting is to allow traffic to enter, pass through and exit the enclosed section safely. This goal implies that drivers drive into the tunnel without reducing their vehicle speed and are able to see unexpected hazards on the carriageway and stop if necessary [15]. During day time, adequate illumination avoids the “black-hole effect” (i.e., a decrease of the drivers’ visual perception) while passing from the outside into the tunnel [16,17]. Therefore, different methods and technologies have been adopted to reduce lighting energy and costs, especially in road tunnels [18,19,20,21].
Recently, research has focused on the use of sunlight to reduce energy consumption [22] and related environmental impacts [23]. In some cases, it is possible to use the natural light in an open stretch of the road before the tunnel entrance, that is, a pre-tunnel lighting (PTL) structure is positioned before the access to the “natural” tunnel [24,25]. A PTL is a reticular structure that reduces the luminance in the access zone [26,27]. Tension structures at the tunnel entrance shift the zones with the highest energy consumption; their effectiveness depends on the geometry and orientation, latitude and longitude of the tunnel [28,29]. The construction of these structures implies significant design and construction costs, but the life cycle cost analysis has revealed their economic advantage with respect to the “zero option”. Pergolas imply lower energy savings and easier maintenance than tension structures [30]. The introduction of sunlight inside the tunnel with light-pipes [31] or optical fibers [32] is another option for more sustainable tunnels, but this strategy is difficult to use because of the relative position between the sun and light-pipes matrix [33]. When it is not possible to use natural light, the inner surfaces of the tunnel play a crucial role in the tunnel lighting design [34]. For this purpose, the pavement reflection coefficient in the visible spectrum has been recently analyzed as a saving strategy. Salata et al. [16] analyzed four alternative solutions to optimize road tunnel lighting systems with two asphalt pavements with different reflection coefficients and two lighting systems (high-pressure sodium (HPS) luminaries, or HPS and light emitting diode (LED) luminaries). Special asphalts with a high-reflection coefficient reduce the power required, and the energy savings balance their higher installation costs. On the other hand, concrete (light) pavements result in 29% less road tunnel lighting costs compared to traditional asphalt (or black) surfaces; calculations for Italian road tunnel pavements performed by Moretti and Di Mascio [35] have confirmed this. Moreover, the use of concrete instead of bituminous pavements implies a higher level of safety in both ordinary and emergency conditions. Indeed, compared to a flexible pavement, a rigid pavement requires less maintenance activities (which interfere with the traffic flow) [36] and it is not combustible in case of fire [23].
Recently, extensive interest in LED has given rise to new lighting systems in tunnels. LED is the most efficient available technology. Its main characteristics are long life, energy efficiency, environmental friendliness, and zero UV emissions; also, LED illumination produces little infrared light and close to no UV emissions, and excellent color rendering [37]. This technology has been adopted by the Italian government-owned road company ANAS (acronym for Azienda Nazionale Autonoma delle Strade—National Autonomous Roads Corporation, Rome, Italy) to rehabilitate lighting systems in its managed tunnels. In 2018, it launched the Greenlight project, which involves more than 700 tunnel tubes where HPS will be replaced by LED luminaries.

2. The Greenlight Project

The Greenlight project provides for rehabilitation works on road tunnel lighting systems, which consist of replacing outdated high-pressure sodium (HPS) luminaries with state-of-the-art light emitting diode (LED) luminaries. The new devices are equipped in order to wirelessly control the light flow and the energy consumption. The implemented remote control allows adjusting the luminous flux with a point-to-point regulation for each LED luminaire. The wireless management and control system aims to adapt the luminance curve to the different conditions of external brightness, and to diagnose the functional status of the individual projectors. Therefore, the luminous flux can be continuously adjusted according to the external luminance for the reinforcement circuits, and according to the daily time bands for the permanent lighting circuits. LED technology makes it possible to optimize the dimming levels up to 15–20% of their initial flow while maintaining the required perceptive conditions and ensuring a significant reduction in consumption. During the night-time hours, the required visibility conditions inside the tunnel are comparable to those of the open-air sections [16]; only the permanent lighting system is necessary to guarantee the required luminance level. To further reduce consumption, a luminous flux regulation system is also installed to manage permanent lighting according to the reduction in traffic at night.
Compared to SAPs, which only allow a step adjustment for homogeneous groups of fixtures, this technical difference ensures considerable savings for the road manager as it reduces costs and allows for operation flexibility in case of the addition or removal of new elements.
Moreover, the project aims not only to reduce consumption and optimize of tunnel lighting systems, but also to raise safety levels. Indeed, the new luminaries enhance the visibility and quality of the diffusion of artificial lighting inside the tunnel. This is due to the higher color-rendering index (CRI) of LED compared to HPS. CRI is a measure of a light source’s ability to show object colors realistically or naturally: the higher the CRI, the better the color perception. Statistically LEDs have CRI values between 70 and 90 or more, while HPS have CRI values not higher than 70 [38]. Road lighting can use lighting systems that have a CRI below 70 because color rendering is not a major issue. However, LEDs offer significant color advantages over HPS, eliminating the monochromatic black appearance of objects illuminated by sodium-bulbs. Therefore, LEDs allow a further reduction in the electricity used for lighting in addition to their longer service life (LED devices have warranty coverage up to 11 years of continuous operation).
Of a total of 1900 tunnels under management, the project involves about 700 tunnel tubes in Italian territory. Greenlight has been divided into eight geographical areas (Figure 1) and two phases with the overall cost estimated as € 155 million (Table 1).
The first phase started in 2018 and is still ongoing: it involves the 147 tubes with the highest energy consumption per unit of length and the overall estimated cost is € 30 million at the end of 2020. Data and the allotted amounts for phase 1 are listed in Table 2.
All works consists of:
  • Substitution of old and inefficient lighting HPS systems with more recent and better performing LED ones
  • Substitution of the power supply cables
  • Substitution of switchboard systems in enclosures
  • Installation of control units and brightness probes.
Therefore, there are no modifications, substitutions, or alterations of the existing position and number of luminaries, in both the interior zone and the adaptation zone. Energy-efficient equipment and technologies have been planned in order to monitor the systems and to control the functionality of the equipment during its service life.

3. Methods

The new lighting systems comply with the Italian standard UNI 11095:2011 Lighting of road tunnels [39]. It divides the longitudinal section of a road tunnel into five zones with different levels of required luminance [40,41] as follows:
  • Access zone: the stretch of road just before the entrance portal. Its length is equal to the stopping distance at the relevant driving speed. The required luminance value ensures the early and safe detection of an obstacle without reduction in driving speed.
  • Threshold zone: the first tunnel section is equal in length to the stopping distance at design speed. The required luminance value is affected by external luminance, which must remain constant and equal to the outside luminance through half the length of the threshold zone, and it is reduced in a linear manner to 40% at the end of the second part of the section.
  • Transition zone: this is the second tunnel section in which luminance values decrease to support the luminance perceived by the driver’s eye.
  • Interior zone: the internal stretch with a constant luminance value. Its minimum value depends on the design speed and the expected traffic flow. The luminance value of the interior zone is the major difference between European legislated levels of tunnel lighting CIE 88:2004 [42] and the Italian standard UNI 11095 [39]. The former does not set an objective luminance value while the Italian standard establishes a minimum value.
  • Exit zone: the final stretch where it is possible to increase the luminance level close to the exit. Such reinforcement/adaptation lighting is not a design constraint for the UNI 11095 standard.
Each zone requires different minimum luminance values as a consequence of the design speed, the meteorological visibility distance, the horizontal lighting in the access zone, the natural luminance, and the optics type, and are calculated using Equations (1)–(3)
Le = c × Lv = c (Lseq + Latm + Lpar + Lcru)
Lt = Le/(1.9 + t)1.4
Lt ≥ 2 × Lr
where Le is the maximum luminance value of Lv; c is a coefficient, which depends on the optics; Lv is the veiling luminance; Lseq is the equivalent veiling luminance; Latm is the atmospheric luminance; Lpar is the luminance of the windshield; Lt is the average luminance value in the transition zone; Lcru is the luminance of the dashboard; t is the travel time in the transition zone; Li is the minimum luminance of the permanent lighting circuit; and Lr is the reference luminance value according to [39]. Lseq is calculated according to the L20 method, which considers the average value of the luminance in a visual cone of 20°, centred on the line of sight of the driver from the beginning of the access zone.
Since the project involves existing tunnels, no modifications were made to the input data with regard to design speed, meteorological visibility distance, horizontal lighting in the access zone, and natural luminance. Therefore, the stopping distance and the threshold luminance remained the same. The lighting system of each tunnel is composed of one permanent and several reinforcement installations. All devices are arranged in a quincunx geometric pattern in both systems. Counter beam optics create the maximum contrast between existing objects and the road because luminaires are placed above the traffic lanes. The minimum luminous efficacy of each LED luminaire was 105 lm/W and its correlated colour temperature (CCT) was 4000 K; for existing HPS luminaries these average characteristics were 95 lm/W and 2000 K, respectively.
Uniformity performances were settled in agreement with UNI 11095 [39] and UNI EN 13201-2 [43]; these standards require parameters for night-time and daytime, and for each regulation state of the lighting system, which are:
  • U0 and Ut ≥ 0.50 over the carriageway or over one-way lanes;
  • U0 and Ut ≥ 0.40 over all other surfaces and over bi-directional lanes
In areas with constant level of luminance, the standards required are:
  • Ul ≥ 0.70 over the carriageway
  • Ul ≥ 0.60 over all other surfaces
where:
  • U0 is the general luminance uniformity, that is, the ratio between the minimum and the average of luminance values [43].
  • Ul is the longitudinal luminance uniformity, that is, the ratio between the minimum and the maximum of luminance values [43] determined along the median axle of a lane for the carriageway.
  • Ut is the transversal luminance uniformity, that is, the ratio between the minimum and the average of luminance values in the same calculus surface section [39].
The software LITESTAR 4D Litecalc [44] was used to design the new lighting systems. It models and verifies the lighting design of road tunnels, and provides numeric and rendered solutions simulating the effects of lighting (shadows, reflections, colour vision and rendering volumes) and obtains a picture of the lighted environment. According to the Italian standard UNI 10439:2001 [45], the assumed maintenance coefficient is equal to 0.8 and the average luminance coefficient is 0.7. These values coincide with those adopted for designing HPS systems.
The adopted software was proven to be suitable for lighting design, since it has an open database where the operator can save product data, do product research, process photometries and spectra or update data automatically; the software was used to realize a real simulation of the results obtained by means of the designed lighting system.
With regard to the lighting design criteria, as previously stated, the luminaires that constitute the permanent lighting system were placed in the same position of the ones previously installed in the tunnel. Each luminaire is equipped with a luminous flux regulation system (transmission module), which communicates with a control unit placed in the cabin. The reinforcement circuits are managed through the veil sensors placed on the external side of the portals, while the permanent lighting circuits are managed through pre-established time cycles. All lighting devices can be modulated to maximize the energy saving performances.
In spite of the design constraints (especially the fixed position of the luminaires), the results of the simulation were satisfying and met all the standard requirements; in particular, with regard to the uniformity, the calculated values generally vary between 0.80 and 0.95 for Ul and between 0.60 and 0.90 for U0.
Lighting energy and cost calculation take into account the power regulation during the day and the year, for both variations in external luminance and for energy saving.

4. Results

Having referenced the current energy consumption to light the tunnels involved in the first phase of Greenlight, Table 3 summarizes the calculated yearly energy savings for each lot and its overall value. The listed values take into account the switching control and the variable absorbed power during the day (day and night hours) and during the year (sunny, cloudy, or rainy days).
For each tunnel, the yearly energy saving represents up to 65% of the current yearly energy consumption related to lighting; the value depends on geographical, traffic, and meteorological conditions. At present, the yearly overall consumption for lighting all tunnels managed by ANAS is about 220 GWh, of which 51 GWh is used for the tunnels involved in phase 1 of Greenlight. Therefore, the average energy saving is 55%: this result has both economic and environmental consequences.
Given the average Italian electricity price is 0.16 €/kWh, the economic results and savings obtained in the first phase of Greenlight are listed in Table 4. Moreover, these savings have environmental implications: the saved tons of oil equivalent (TOE) were calculated. According to the Italian Authority for Energy and Gas, the conversion factor of electric energy into primary energy is 0.187 TEP/MWh, and this is the reference value that was adopted to evaluate the effectiveness of the energy efficiency measures.
Taking into account the expected rebates in the tender phases, ANAS estimated that the actual investment is 30 million euro. Therefore, the economic gains from saving electricity consumption ensure a breakeven point at 7 years after the rehabilitation works, when the project will return its initial investment.
In regard to the environmental issue, the saved impacts from energy non-consumption were calculated using the software package SimaPro 8.0.5.13 [46]. A Life Cycle Impact Assessment was implemented to evaluate the saved environmental impacts in relation to the electricity savings listed in Table 3. The database Ecoinvent 3 was used to assess the parameters describing environmental impacts according to the characterization factors listed in EN 15804:2012+A1:2013 [47]. The examined environmental impact categories (ICs) were: Global Warming Potential (GWP), Ozone layer Depletion Potential (ODP), Acidification Potential (AP), Eutrophication Potential (EP), Photochemical oxidation Potential (POCP), Abiotic depletion-elements (ADP-e), and Abiotic depletion-fossil fuels (ADP-f).
The processes included in the environmental analysis of the transmission of high voltage electricity were electricity production in Italy and from imports, the transmission network and the electricity losses. In order to obtain reliable results consistent with the Italian energy market, the production mix was composed of 36.6% of renewable primary energy and 63.4% of non-renewable primary energy (Table 5).
Table 6 lists the impact categories that were avoided annually due to the total yearly energy saving listed in Table 3.
The Greenlight project represents a big effort on the part of ANAS, the Italian government-owned road company to rehabilitate and improve the lighting systems in its tunnels. The investments are significant, for example, for the rehabilitation works completed in 2018, the total cost was 6 million euros (Figure 2), and in 2019, works worth 13.5 million euros are in progress or planned (Table 7).
Data in Table 7 were also analyzed in order to correlate the required investment to the tunnel length (L): Figure 3 shows the results obtained for 32 tunnels (their overall length is 39,663 m) of phase 1.
As shown in Figure 3, a correlation curve between L and the lighting rehabilitation cost per unit length (cl) was identified (Equation (4)):
cl = 182339 L−0.901
where L is expressed in m and cl is in €/m.
The coefficient of determination R2 of the dashed trend line is 0.87. The obtained curve is valid under two important hypotheses about the cost of luminaries and the layout of the lighting systems.
With regard to the cost, the unit prices comply with those currently valid in Italy [49]; the price of each luminaire ranges between € 395 for elements with less than 3000 lm luminous flux and € 1798 for elements with more than 41,500 lm luminous flux. Regarding the layout of the lighting systems, the number and the position of LED luminaries coincide with those of existing HPS luminaries. Thus, the distance between LEDs could be less without the restriction of having to replace the HPS at the same distance, and the total initial cost of the luminaires in the interior zones could be higher.

5. Discussion

For ANAS, tunnel lighting is the principal cost item in the energy budget expenditure: at present, the yearly consumption for tunnel lighting is about 230 GWh. Therefore, the Greenlight multi-year project aims to reduce energy consumption for lighting in its road tunnels. It consists of using equipment and technologies characterized by high energy efficiency (i.e., LED luminaries) and balancing environmental-economic needs and the operational limits due to pre-existing structures.
Greenlight aims to improve and standardize safety standards and service to road customers, as well as to optimize energy consumption, especially in more energy-intensive lighting systems. The high CRI, the luminous efficiency and the high visual comfort of LED luminaries allow for significant reductions in the energy consumption with the same luminance on the road surface. For each luminaire considered in the project, the minimum CRI is 80, the minimum luminous efficacy is 105 lm/W, and its CCT is 4000 K. Furthermore, the installation of luminance sensors at tunnel entrances permits the internal luminance to be monitored continuously and verifies the state of efficiency and reliability of the system. Lighting monitoring is ensured by specific latest-generation software and its results are dealt with in real time. Moreover, in contrast to the HPS luminaries, during day hours this type of luminaire permits point-by-point adjustment of the internal illumination in accordance to the external luminance, in order to optimize the luminous flux. Therefore, the wireless management and control system diagnoses the functional status of the individual projectors, and also adapts the brightness of each luminaire to different conditions. During night hours, only permanent lighting remains in operation to guarantee the required luminance level. In order to further reduce consumption, a luminous flux adjustment system is also installed for permanent lighting, which takes into account the reduction of vehicular traffic at night.
The benefits arising from Greenlight are related to users’ safety, road management savings, and environmental protection. ANAS estimates that the return on investment is 7 years, this has been calculated considering only energy savings, without the cost of maintenance. Therefore, the return on investment could be a shorter time because of the durability of LED which is greater than HPS. Considering the costs and the effectiveness of the investment, it should also be noted that the knowledge gained to date suggests there is a correlation between the lighting rehabilitation cost and the length of the tunnel. This analysis was presented above (see Figure 3) and this finding might help to expedite the assessment of the cost of road tunnel LED lighting systems: it fits with the variability in lighting rehabilitation costs per unit length that is caused by the luminance requirements laid down by the reference standard UNI 11095.

6. Conclusions

Renewal of technologies and energy rationalization processes could contribute to meeting the sustainability targets set by the European Union on climate and energy. Within this framework, ANAS, the Italian government-owned road company launched the Greenlight project to replace HPS tunnel lighting systems with state-of-the-art LED luminaries. The new systems will reduce electricity consumption by up to 50% of the current values; additionally, the lighting quality inside the tunnel will be enhanced thanks to better uniformity and color temperature of the new luminaries.
The initiative is composed of two phases: the first one will account for 45 million euros and the second one for about 110 million euros. Until now, the on-going first phase involves 147 tubes: their new lighting systems cost 30 million euros (allotment volume) and ensure 28 GWh saved energy every year (on average 55% of the current consumption). The economic saving provides a total return over less than seven years and has direct environmental effects. According to the European standard EN 15804, the avoided yearly emissions of greenhouse gases are 17,000 t of CO2 eq., while saved abiotic and fossil resources are 19.3 kg of Sb and 230 TJ, respectively.
The presented on-the-field experience permitted us to correlate the tunnel length to the rehabilitation cost per unit length; the high value of the coefficient of determination corroborated the result, which could be useful to road managers pursuing environmental, economic and safety goals with tunnel LED lighting.

Author Contributions

Conceptualization, L.M. and G.C.; Data curation, L.C., F.B., V.C. and S.N.; Formal analysis, L.M. and G.C.; Investigation, L.M. and G.C.; Methodology, L.M. and G.C.; Project administration, L.C.; Software, F.B., V.C. and S.N.; Supervision, L.C.; Validation, F.B.; Visualization, V.C. and S.N.; Writing—original draft, L.M. and G.C.; Writing—review & editing, L.M. and G.C.

Funding

This research received no external funding.

Conflicts of Interest

The authors declare no conflict of interest.

References

  1. European Commission. Green Paper on Energy Efficiency or Doing More with Less; European Commission: Brussels, Belgium, 2005. [Google Scholar]
  2. Miccoli, S.; Finucci, F.; Murro, R. Assessing project quality: A multidimensional approach. Adv. Mater. Res. 2014, 1030–1032, 2519–2522. [Google Scholar] [CrossRef]
  3. Miccoli, S.; Finucci, F.; Murro, R. Measuring shared social appreciation of community goods: An experiment for the east elevated expressway of Rome. Sustainability 2015, 7, 15194–15218. [Google Scholar] [CrossRef]
  4. European Commission. Green Paper Lighting the Future Accelerating the Deployment of Innovative Lighting Technologies; European Commission: Brussels, Belgium, 2011. [Google Scholar]
  5. European Technology Platform Photonics21. Lighting the Way Ahead Photonics21 Strategic Research Agenda; Photonics21: Susseldorf, Germany, 2010. [Google Scholar]
  6. Terna. Consumi Energia Elettrica per Settore Merceologico Italia. 2018. Available online: https://www.terna.it/it-it/sistemaelettrico/statisticheeprevisioni/consumienergiaelettricapersettoremerceologico.aspx (accessed on 17 May 2019).
  7. CEN. CEN/TR 13201-1:2014. In Road Lighting—Part 1: Guidelines on Selection of Lighting Classes; Technical Report; European Commitee for Standardization: Brussels, Belgium, 2014. [Google Scholar]
  8. CEN. CEN/TR 13201-1:2004. In Road Lighting. Selection of Lighting Classes; Technical Report; European Committee for Standardization: Brussels, Belgium, 2004. [Google Scholar]
  9. Wojnicki, I.; Komnata, K.; Kotulski, L. Comparative study of road lighting efficiency in the context of CEN/TR 13201 2004 and 2014 lighting standards and dynamic control. Energies 2019, 12, 1524. [Google Scholar] [CrossRef]
  10. Wojnicki, I.; Kotulski, L. Empirical study of how traffic intensity detector parameters influence dynamic street lighting energy consumption: A case study in Krakow, Poland. Sustainability 2018, 10, 1221. [Google Scholar] [CrossRef]
  11. Löfsjögård, M.; Silfwerbrand, J. Proposal for improvement of road lighting design for concrete roads. Road Mater. Pavement Des. 2004, 5, 193–213. [Google Scholar] [CrossRef]
  12. Doulos, T.; Sioutis, I.; Kontaxis, P.A.; Zissis, G.; Faidas, K. A decision support system for assessment of street lighting tenders based on energy performance indicators and environmental criteria: Overview, methodology and case study. Sustain. Cities Soc. 2019, 51, 101759. [Google Scholar] [CrossRef]
  13. Pasolini, G.; Toppan, P.; Zabini, F.; Castro, C.D.; Andrisano, O. Design, deployment and evolution of heterogeneous smart public lighting systems. Appl. Sci. 2019, 9, 3281. [Google Scholar] [CrossRef]
  14. Doulos, T.; Sioutis, I.; Tsangrassoulis, A.; Canale, L.; Faidas, K. Minimizing lighting consumption in existing tunnels using a no-cost fine-tuning method for switching lighting stages according revised luminance levels. In Proceedings of the IEEE International Conference on Environment and Electrical Engineering and 2019 IEEE Industrial and Commercial Power Systems Europe (EEEIC/I&CPS Europe), Genova, Italy, 11–14 June 2019; pp. 1–6. [Google Scholar] [CrossRef]
  15. Wenchenga, C.; Zhengb, H.; Lipinga, G.; Yandana, L.; Dahua, C. Performance of induction lamps and HPS lamps in road tunnel lighting. Tunn. Undergr. Space Technol. 2008, 23, 139–144. [Google Scholar] [CrossRef]
  16. Salata, F.; Golasi, I.; Bovenzi, S.; de Lieto Vollaro, E.; Pagliaro, F.; Cellucci, L.; Coppi, M.; Gugliermetti, F.; de Lieto Vollaro, A. Energy optimization of road tunnel lighting systems. Sustainability 2015, 7, 9664–9680. [Google Scholar] [CrossRef]
  17. Salata, F.; Golasi, I.; Poliziani, I.; Futia, A.; de Lieto Vollaro, E.; Coppi, M.; de Lieto Vollaro, A. Management optimization of the luminous flux regulation of a lighting system in road tunnels. A first approach to the exertion of predictive control systems. Sustainability 2016, 8, 1092. [Google Scholar] [CrossRef]
  18. Maheswari, C.; Jeyanthi, R.; Krishnamurthy, K.; Sivakumar, M. Implementation of energy management structure for street lighting systems. Modern Appl. Sci. 2009, 3, 31–37. [Google Scholar] [CrossRef]
  19. Sunky, Z.; Mohit, P. Lighting design of an urbanized tunnel. Present at the Seminar Series 2012 Part 4 Research Projects, The University of Auckland, Auckland, New Zealand, 6–7 September 2012. [Google Scholar]
  20. Rabazan, O.; Peña-García, A.; Pérez-Ocón, F.; Gómez-Lorente, D. A simple method for designing efficient public lighting, based on new parameter relationships. Exp. Syst. Appl. 2013, 40, 7305–7315. [Google Scholar] [CrossRef]
  21. Peña-García, A.; López, J.C.; Grindlay, A.L. Decrease of energy demands of lighting installations in road tunnels based in the forestation of portal surroundings with climbing plants. Tunn. Undergr. Space Technol. 2015, 46, 111–115. [Google Scholar] [CrossRef]
  22. Peña-García, A. The SLT equation: A tool to predict and evaluate energy savings in road tunnels with sunlight systems. Tunn. Undergr. Space Technol. 2017, 64, 43–50. [Google Scholar] [CrossRef]
  23. Cantisani, G.; Di Mascio, P.; Moretti, L. Comparative Life Cycle Assessment of lighting systems and road pavements in an Italian twin-tube road tunnel. Sustainability 2018, 10, 4165. [Google Scholar] [CrossRef]
  24. Cantisani, G.; D’Andrea, A.; Moretti, L. Natural lighting of road pre-tunnels: A methodology to assess the luminance on the pavement—Part I. Tunn. Undergr. Space Technol. 2018, 73, 37–47. [Google Scholar] [CrossRef]
  25. Cantisani, G.; D’Andrea, A.; Moretti, L. Natural lighting of road pre-tunnels: A methodology to assess the luminance on the pavement—Part II. Tunn. Undergr. Space Technol. 2018, 73, 170–178. [Google Scholar] [CrossRef]
  26. Drakou, D.; Celucci, L.; Burattini, C.; Nardecchia, F.; Gugliermetti, F. Study of a daylight “filter” in a pre-tunnel structure. In Proceedings of the International Conference on Environment and Electrical Engineering, Rome, Italy, 10–13 June 2015; pp. 649–652. [Google Scholar]
  27. Drakou, D.; Celucci, L.; Burattini, C.; Nardecchia, F.; Gugliermetti, F. Study for optimizing the daylight “filter” in a pre-tunnel structure. In Proceedings of the IEEE Conference 2016, Florence, Italy, 6–10 June 2016. [Google Scholar]
  28. Peña-García, A.; Gil-Martín, L.M.; Escribano, R.; Espín-Estrella, A. A scale model of tension structures in road tunnels to optimize the use of solar light for energy saving. Int. J. Photoenergy 2011, 2011, 9. [Google Scholar] [CrossRef]
  29. Peña-García, A.; Escribano, R.; Gil-Martín, L.M.; Espín-Estrella, A. Computational optimization of semi-transparent tension structures for the use of solar light in road tunnels. Tunn. Undergr. Space Technol. 2012, 32, 127–131. [Google Scholar] [CrossRef]
  30. Peña-García, A.; Gil-Martín, L.M. Study of pergolas for energy savings in road tunnels. Comparison with tension structures. Tunn. Undergr. Space Technol. 2013, 35, 172–177. [Google Scholar] [CrossRef]
  31. Gil-Martín, L.M.; Peña-García, A.; Jimenez, A.; Hernández-Montes, E. Study of light-pipes for the use of sunlight in road tunnels: From a scale model to real tunnels. Tunn. Undergr. Space Technol. 2014, 41, 82–87. [Google Scholar] [CrossRef]
  32. Qin, X.; Zhang, X.; Qi, S.; Han, H. Design of solar optical fiber lighting system for enhanced lighting in highway tunnel threshold zone: A case study of Huashuyan tunnel in China. Int. J. Photoenergy 2015, 2015, 10. [Google Scholar] [CrossRef]
  33. Peña-García, A.; Gil-Martín, L.M.; Hernández-Montes, E. Use of sunlight in road tunnels: An approach to the improvement of light-pipes’ efficacy through heliostats. Tunn. Undergr. Space Technol. 2016, 60, 135–140. [Google Scholar] [CrossRef]
  34. Fotios, S.; Boyce, P.; Ellis, C. The effect of pavement material on road lighting performance. Light. J. 2005, 71, 35–40. [Google Scholar]
  35. Di Mascio, P.; Moretti, L. Concrete vs. asphalt: Pavement and lighting costs in Italian road tunnels. In ACI Special Publication SP-326 Durability and Sustainability of Concrete Structures, Proceedings of the 2nd Workshop on Durability and Sustainability of Concrete Structures, Moscow, Russia, 6–7 June 2018; American Concrete Institute: Farmington Hills, MI, USA, 2018. [Google Scholar]
  36. Jung, Y.; Freenman, T.J.; Zollinger, D.G. Guidelines for Routine Maintenance of Concrete Pavement; FHWA/TX-08/0-5821-1; Federal Highway Administration: Austin, TX, USA, 2008. [Google Scholar]
  37. Peña-García, A.; Lai Nguyen, T.P. A global perspective for sustainable highway tunnel lighting regulations: Greater road safety with a lower environmental impact. Int. J. Environ. Res. Public Health 2018, 15, 2658. [Google Scholar] [CrossRef]
  38. Rodrigues, C.R.; Almeida, P.S.; Soares, G.M.; Jorge, J.M.; Pinto, D.P.; Braga, H.A. An experimental comparison between different technologies arising for public lighting: LED luminaires replacing high pressure sodium lamps. In Proceedings of the IEEE International Symposium on Industrial Electronics, Gdansk, Poland, 27–30 June 2011; pp. 141–146. [Google Scholar]
  39. Ente Nazionale Italiano di Normazione [UNI]. UNI 11095:2011: Illuminazione Delle Gallerie Stradali; UNI: Milan, Italy, 2011. (In Italian) [Google Scholar]
  40. Moretti, L.; Cantisani, G.; Di Mascio, P. Management of road tunnels: Construction, maintenance and lighting costs. Tunn. Undergr. Space Technol. 2016, 51, 84–89. [Google Scholar] [CrossRef]
  41. Moretti, L.; Cantisani, G.; Di Mascio, P.; Caro, S. Technical and economic evaluation of lighting and pavement in Italian road tunnels. Tunn. Undergr. Space Technol. 2017, 65, 42–52. [Google Scholar] [CrossRef]
  42. Commission Internationale de l’Eclairage [CIE]. Guide for the Lighting of Road Tunnels and Underpasses; CIE 88-2004; Commission Internationale de l’Eclairage: Vienna, Austria, 2004. [Google Scholar]
  43. Ente Nazionale Italiano di Normazione [UNI]. UNI EN 13201:2016: Illuminazione Stradale—Parte 2: Requisiti Prestazionali; UNI: Milan, Italy, 2016. (In Italian) [Google Scholar]
  44. Oxytech. Litestar 4D Litecalc. In Manuale dell’Utente; OxyTech srl: Milano, Italy, 2018. [Google Scholar]
  45. Ente Nazionale Italiano di Normazione (UNI). UNI 10439:2001: Illuminotecnica—Requisiti Illuminotecnici delle Strade Con Traffico Motorizzato; UNI: Milan, Italy, 2001. (In Italian) [Google Scholar]
  46. SimaPro 8.0.5.13. Software SimaPro. Pré; Consultants: Amersfoort, The Netherlands, 2016. [Google Scholar]
  47. European Committee for Standardization (EN). Sustainability of Construction Works—Environmental Product Declarations—Core Rules for the Product Category of Construction Products; EN 15804:2012+A1:2013; European Committee for Standardization: Brussels, Belgium, 2013. [Google Scholar]
  48. Gestione Servizi Energetici. Fuel Mix, Determinazione del Mix Energetico per Gli Anni 2016–2017; Gestore dei Servizi Energetici GSE S.p.A.: Rome, Italy, 2018; Available online: https://www.gse.it/servizi-per-te/fuel-mix-determinazione-del-mix-energetico-per-gli-anni-2016-2017 (accessed on 18 July 2019).
  49. ANAS. Elenco prezzi Nuove Costruzioni e Manutenzione Straordinaria; ANAS: Rome, Italy, 2018. [Google Scholar]
Figure 1. Greenlight project locations.
Figure 1. Greenlight project locations.
Sustainability 11 04631 g001
Figure 2. Completed works in 2018.
Figure 2. Completed works in 2018.
Sustainability 11 04631 g002
Figure 3. Tunnel length vs. rehabilitation lighting costs per unit length.
Figure 3. Tunnel length vs. rehabilitation lighting costs per unit length.
Sustainability 11 04631 g003
Table 1. Characteristics of Greenlight.
Table 1. Characteristics of Greenlight.
LotNumber of TubesOverall Length of Tubes (km)Amount of Estimated Cost (€)
L1927022,900,000
L2654513,500,000
L31458523,800,000
L4897521,000,000
L51128023,500,000
L61177422,300,000
L7495816,900,000
L8394511,700,000
Total708532155,000,000
Table 2. Characteristics of phase 1 Greenlight.
Table 2. Characteristics of phase 1 Greenlight.
LotNumber of TubesOverall Length of Tubes (km)Amount Allotted (€)
L11120.373,667,000
L21122.223,333,000
L32129.415,000,000
L41922.224,000,000
L52026.674,000,000
L64024.074,333,000
L71620.003,000,000
L8917.782,667,000
Total147182.7430,000,000
Table 3. Yearly energy savings—first phase.
Table 3. Yearly energy savings—first phase.
LotYearly Energy Saving (MWh)
L13423
L23111
L34667
L43733
L53733
L64044
L72800
L82489
Total28,000
Table 4. Economic and environmental results—first phase.
Table 4. Economic and environmental results—first phase.
LotYearly Saving from Electricity Consumption (€)Yearly Saved TOE (t of Oil Equivalent)
L13,667,000640.01
L23,333,000781.72
L35,000,000872.67
L44,000,000698.13
L54,000,000698.13
L64,333,000756.25
L73,000,000523.6
L82,667,000465.48
Total4,480,0005236.00
Table 5. Electricity production mix in Italy [48].
Table 5. Electricity production mix in Italy [48].
SourceProduction Share (%)
Coal13.75
Natural gas42.34
Oil and other7.31
Hydro14.64
Solar7.68
Wind5.86
Biomass6.22
Geothermic2.20
Table 6. Avoided impact categories—first phase.
Table 6. Avoided impact categories—first phase.
ICAmountUnits
GWP1.78 × 107kg CO2 eq.
ODP1.35 × 100kg CFC-11 eq.
AP6.18 × 104kg SO2 eq.
EP1.51 × 104Kg (PO4)3- eq.
POCP1.84 × 104kg C2H4 eq.
ADP-e1.93 × 101kg Sb eq.
ADP-f2.32 × 108MJ
GWP1.78 × 107kg CO2 eq.
Table 7. Planned and on-going works in 2019.
Table 7. Planned and on-going works in 2019.
LotPlanned and On-Going Works (€)
L11,177,750
L21,869,690
L33,059,210
L42,573,350
L51,330,420
L62,857,680
L70
L8687,270
Total13,555,370

Share and Cite

MDPI and ACS Style

Moretti, L.; Cantisani, G.; Carrarini, L.; Bezzi, F.; Cherubini, V.; Nicotra, S. Italian Road Tunnels: Economic and Environmental Effects of an On-Going Project to Reduce Lighting Consumption. Sustainability 2019, 11, 4631. https://doi.org/10.3390/su11174631

AMA Style

Moretti L, Cantisani G, Carrarini L, Bezzi F, Cherubini V, Nicotra S. Italian Road Tunnels: Economic and Environmental Effects of an On-Going Project to Reduce Lighting Consumption. Sustainability. 2019; 11(17):4631. https://doi.org/10.3390/su11174631

Chicago/Turabian Style

Moretti, Laura, Giuseppe Cantisani, Luigi Carrarini, Francesco Bezzi, Valentina Cherubini, and Sebastiano Nicotra. 2019. "Italian Road Tunnels: Economic and Environmental Effects of an On-Going Project to Reduce Lighting Consumption" Sustainability 11, no. 17: 4631. https://doi.org/10.3390/su11174631

Note that from the first issue of 2016, this journal uses article numbers instead of page numbers. See further details here.

Article Metrics

Back to TopTop