Next Article in Journal
The Optimization of Waterproof and Drainage Design and an Evaluation of the Structural Safety of Tunnels in Weak Watery Strata
Previous Article in Journal
Visualization Analysis of Emergency Exit Signs Literature Based on CiteSpace
 
 
Font Type:
Arial Georgia Verdana
Font Size:
Aa Aa Aa
Line Spacing:
Column Width:
Background:
Article

A New Method for Correcting the Deviation of a Middle Pier Tower of a Long-Span Intermediate Arch Bridge

State Key Laboratory of Mountain Bridge and Tunnel Engineering, Chongqing Jiaotong University, Chongqing 400074, China
*
Author to whom correspondence should be addressed.
Buildings 2023, 13(10), 2498; https://doi.org/10.3390/buildings13102498
Submission received: 10 August 2023 / Revised: 20 September 2023 / Accepted: 28 September 2023 / Published: 30 September 2023

Abstract

:
To control the deviation of a long-span concrete-filled steel tube (CFST) arch bridge during construction monitoring, a practical method for controlling tower deviation is studied and established. The form of construction of this bridge is an intermediate double-arch bridge, which differs from conventional bridges, thus requiring the urgent resolution of the issue of unbalanced middle piers. Therefore, the mechanical characteristics and construction process of an intermediate long-span, dual-coupled steel pipe arch bridge are meticulously examined by using a 1:10 scale model, with particular focus on discussing the deflection of the buckle tower during the installation of the arch rib segments. Construction control is implemented using a novel tower deflection control method that addresses unilateral torsion problems and difficulties in controlling the deflection of the tower. The model results are compared with the finite element analysis output, demonstrating that this new approach can resolve unbalanced tower deviations by maintaining absolute values within 0.5 mm. After correcting these deviations, the measured results from the model bridge tower align with the calculated analytical results and even surpass the theoretical expectations for tower deviation. This remarkable new method accurately resolves real-world bridge tower deviations.

1. Introduction

With the wide application of steel pipe concrete arch bridges, its forms of construction are becoming more diversified [1]. The span of the bridge has developed from just over 100 m in the beginning to nearly 600 m at present [2,3]. The design of a concrete-filled steel tube (CFST) arch bridge is usually guided via finite element simulation, and the use of a scaled model test can not only verify the mechanical performance of the structure, but also preview and evaluate the actual control of the construction. The control of the accuracy of pylon deflection will affect the alignment of such long-span arch bridges [4], but there is little research available into pylon control (especially as related to the middle pier during cable-stayed suspension). At present, some Chinese researchers have studied the linear control of CFST arch bridges in different forms. Gu, Y [5] described arch rib construction technology to analyze arch rib installation control methods from the perspective of arch processing and the splicing of the steel tube based on the arch bridge characteristics and construction-control processes of CFST bridge types. Based on the grey prediction theory, Zhuo Xiaoli [6] established a grey model for line-shape prediction, considering the residual correction during the construction of main beams in the context of mid-span steel box arch bridges, and predicted the construction pre-elevation value of main beam segments through tower deviation. It can be seen that tower deflection and arch rib alignment in arch bridges interact [7,8,9]. The suspension assembly method is a common construction method for long-span arch bridges [10,11,12]. However, the studies on the suspension assembly method mainly focus on improving the accuracy of the cable forces [13], while the studies on tower deflection are few. At present, for a long-span steel truss arch bridge, suspension tower construction is the most difficult and risky part of the construction process. The steel truss arch erection side span of the Jianghan Seventh Bridge is installed by using the support method, and the middle span is installed via the cantilever method. The suspension tower plays an important role in the cantilever erection construction of the steel truss arch. The suspension tower is one of the key structures in the cantilever construction of the steel truss arch bridge, and it connects the cantilever end of the main arch with the balance end of the side beam using the suspension cable, so that the steel truss arch bridge can maintain overall stability during the construction of the main girder [14]. The application of monitoring technology to realize the construction-line monitoring of the suspension tower can not only meet the installation accuracy requirements of the suspension tower members, but also improve the safety and accuracy of subsequent main beam closure [15]. This issue has also been investigated by some foreign researchers in succession. In the large-span concrete arch bridge constructed via the cantilever pouring method [16], path control is key to ensuring construction quality, and the deflection of the buckle tower often affects the arch elevation of each segment. The influence of the deflection of the buckle tower on the elevation of each section during construction was analyzed via a geometric analysis method, and the finite element model was established in Midas software to verify the results. The results show that the deflection of the buckle tower has little effect on the elevation of the arch foot, but it has a greater effect on the elevation of the section near the arch top, and the section at the arch top is more sensitive to the change in the buckle-tower height. According to Jiang Wei [17], the structural state of the main cable of the hoisting system changes during the hoisting process. Based on the engineering background of a large bridge, this paper obtained a high-precision calculation method of the main cable sag and cable force during the hoisting process through theoretical deduction, and estimated the influence of vehicle traffic on the main cable force by numerical simulation. The results show that the proposed method for calculating the sag of the main cable has high accuracy and can be applied in practice. The main cable force increases gradually as the vehicle moves toward the mid-span and the main cable force at the pylon end reaches its maximum when the vehicle is within the span. Some scholars have also shown how to prevent the occurrence of tower deviations by monitoring via three-dimensional scanning, but they have not avoided the occurrence of tower deviations from the root.
In terms of the method of the tower deflection theory, Lin T.M. [18] used the suspension cable element method to derive a formula giving the deflection of the hinged tower of the cable hoisting system where the pressure tower is set, so that the calculation of the cable hoisting construction stage and the tower deflection calculation were unified. A feasibility control system of intelligent tower deviation was verified by theoretical analysis, but it has not been applied in engineering practice. Deng JiangMing [19] derived an analytical formula of the influence of the tower deflection with an integrated button-back on the linear arch rib by using a geometric analysis method. The feasibility of these proposed control systems as applied to intelligent tower deviation was validated by theoretical analysis, but the deformation of the tower is not considered.
In terms of calculation methods, Zhen-guo C et al. [20] considered the influence of the deflection of the buckle tower during the calculation of the cable force, and ascertained the that optimal buckle cable force matrix can be used to reduce the influence of buckle-tower deflection on the alignment of the arch rib. Ke-Jian Y [21] studied the sensitivity of each section of the buckle of the lower part of the buckle-tower to the vertical displacement of the closing hole, and found that too small a horizontal inclination would weaken the influence of the section buckle force on the vertical displacement of the closing hole, and they solved the problem of the low adjustment efficiency of the long buckle cable by calculating an optimal cable force via the formal installation iterative method. However, these two methods tend to be those viewed as lacking in innovation: if the number of iterations is excessive, the calculation will be slow. Xue-Tao D et al. [22] studied the influence of the main cable slip on tower deflection in the design of the cable hoisting system, and found that the main cable slip had a significant influence on the cable hoisting system, which could significantly change the deviation of the top of the tower and the stress thereon. Wei S et al. [23] found that the displacement of the top of the tower in the integrated construction of cables and buckle towers exerts a significant influence on the accuracy of the arch-rib splicing, and the key to construction control is to reduce the deflection of the cable and the buckle tower. Therefore, the initial tension of the wind rope of the top cable should be adjusted while observing the deviation of the tower during the construction of the arch rib assembly, thereby reducing the horizontal cable force difference and keeping the cable and buckle tower in a vertical state as far as possible. The method is novel and unique in its technical aspects, but this method lacks theoretical support.
The safety and construction accuracy of the tower has been studied widely; taking the Changshou Yangtze River Bridge as the background, Gao Z [24] introduced the construction technology of a 60 m high, single-story, suspension tower from the design, construction, and to demolition. Taking the Nanjing Dashingguan Bridge as the background, Sheng Zhiping [25] innovatively laid a suspension tower with three layers of cable stays on the outside of the two-span steel beams, with a height of 68.5 m, and adopted flat cable construction technology on the inside, which overcame the problems of the internal force and alignment adjustment difficulty during the erection of steel beams. Zhi-Hu Z et al. [26], taking the Jianghan Seventh Bridge as the background, conducted the stress analysis of various working conditions of the 89.6-m high sling tower during the assembly process. Renbo F et al. [27] studied the application of 39-m high suspension tower in flexible arch of a continuous steel girder in the Guanhe Super-Bridge on the Lianyan Railway. This long-span bridge has certain advantages and broad prospects for application. Due to its wide range of application, especially in long-span bridges, cable hoisting construction has become the main method of the erection of arch bridges [28,29,30]. When cables are used to lift arch ribs, the processes of each span affect the deformation of the tower, induce deviations, and have linking effects on the arch ribs suspended on the tower. When the linkage effect gradually accumulates, assembly accuracy and tower deviation will be affected if no adjustment is made [31,32]. In the present work, a set of new methods and theories are used to control tower deviation, limiting the occurrence of unbalanced tower deviation and the corresponding torsion at the root, which is different from the methods of other scholars. The problem of tower deviations is solved, and the accuracy of tower deviations is controlled to within the theoretical value, thereby achieving the ideal control effect.

2. Project Overview and Model Design

2.1. Project Overview

The Longtai Expressway is a section of China’s national expressway network planning, which is one of the important links in the main skeleton expressway network planned across the Yangtze River, and is also the main channel from the central region to the south-east coast. The whole line adopts six-lane expressway standard construction. The Tianyun Bridge is one of the controlled, landscape-type, projects of the overall project. Its structure consists of two arch circles, three arch seats, middle piers and bridge panels. The main bridge adopts the main span of 2 × 260 m of a CFST to design the overall subgrade width of 16 m, the design load is Grade I (highway), and the structural safety grade is Grade I. The design speed is 80 km/h, and the bridge structure design life is 100 years. In the middle pier, there are buckle cables on both sides. Using the middle arch seat, sections are constructed on both sides at the same time, and the buckle cables are pulled up to complete its construction. The column on the arch adopts a row-type rectangular section structure, and the column is connected by a cross-beam. The span of the two-span continuous CFST intermediate truss arch is larger in the same type of bridge, the bridge continuously crosses the river, the bridge location on both sides of the mountains makes for difficult access to traffic, and its construction is difficult necessitating the present research into the key technology of design and construction. The general layout of the Tianyun Bridge is shown in (Figure 1).

2.2. Similarity Theory

For structural tests, it is most accurate to use the original actual structure for the simulation, so a certain proportion of model tests are often used, and the force state of the original structure is calculated through the use of the similarity ratio. To simulate the construction process of the Tianyuan Bridge, it is necessary to study the method used to control the tower deflection. To obtain more accurate test results and data, the geometric scaling ratio of the main arch ring, arch base and junction pier is proposed to be 1:10 on the basis of comprehensive consideration of the test content, model materials, production accuracy, and component volume, as well as considering time, economic cost, and data fidelity. The scale ratio of stress is 1:1, and the interface pier is designed in scale according to the ratio of pushing stiffness of 1:10.
From the scale ratio of geometry and force, the similarity coefficients are obtained according to the similarity theory as follows (Table 1):

2.3. Component Design

2.3.1. Arch Rib Design

According to the relevant design drawings of the Tianyun Bridge and the existing conditions, the values of the geometric similarity ratio of the main structural dimension are as per (Table 2).

2.3.2. Arch Design

Due to this scaling model study, there are almost half spans on both sides. To make the scale model simulate the internal force and deformation of the real bridge, the arch design is strictly scaled down to ensure that the model undergoes no displacement in the construction and test process, which is aligned with reality. The arch seat diagram is shown in Figure 2.

2.3.3. Pier Design

The height of the pier proposed in this design is 4.5 m + 1.5 m. The model test uses a steel tower pier (Figure 3).

3. Finite Element Analysis

3.1. Finite Element Model

The Midas finite element model is established based on the 1:10 scale model test. There are 2035 nodes and 3776 units in the whole bridge, among which the cable is a tension-only truss unit, and the main arch and tower are beam units. The simulation is conducted according to the hoisting sequence of the actual bridge during the construction stage.
For the convenience of description, the following is the partition diagram (Figure 4), for example: A2 is the second section of Side A.

3.2. Tower Deviation Calculation

The focus of the present research is the deviation of the middle pier tower. The deviation of the tower during normal construction is calculated: there are eight sections of the arch bridge, and some key sections are listed here, such as Section 2, Section 6, and Section 8. The outputs from the finite element analysis model are as follows:
Working condition 1: Hoisting arch rib A side of Section 2.
Working condition 2: Hoisting arch rib B side of Section 2.
In condition A2 (Figure 5), the unbalanced horizontal thrust is generated by unilateral lifting, with a 0.1 mm displacement at the bottom of the pier, a 0.88 mm displacement at the mid-point of the pier, and a 1.6 mm displacement at the top of the pier. In condition B2 (Figure 6), due to the balanced horizontal thrust generated by lifting on both sides, there is almost no displacement at the top of the pier. The maximum stress on the bottom of the tower is 52 MPa.
Working condition 3: Lifting Section 6 on side D of the arch rib.
Working condition 4: Lifting Section 6 on side C of the arch rib.
In condition D6 (Figure 7), the unbalanced horizontal thrust is generated by unilateral lifting. The displacement at the bottom of the pier is 0.1 mm, the displacement at the middle of the pier is about 0.9 mm, and the displacement at the top of the pier is 2.51 mm. In condition C6 (Figure 8), due to the balanced horizontal thrust generated by lifting on both sides, there is almost no displacement at the top of the pier. The maximum stress on the bottom of the tower is 82 MPa.
Working condition 5: Lifting Section 8 on side A of the arch rib.
Working condition 6: Lifting Section 8 on side B of the arch rib.
In condition A8 (Figure 9), the unbalanced horizontal thrust is generated by unilateral lifting. The displacement at the bottom of the pier is 0.1 mm, the displacement at the middle of the pier is about 0.78 mm, and the displacement at the top of the pier is 2.85 mm. In condition B|8 (Figure 10), due to the balanced horizontal thrust generated by lifting on both sides, there is almost no displacement at the top of the pier. The maximum stress on the bottom of the tower is 118 MPa.
The column deviation data under a normal construction sequence are listed below; these lay a foundation for the comparison of the data of new construction methods.

4. New Methods of Control Theory

4.1. Control Method

In this method, the single-side segment and the arch rib segment on the symmetrical side are hoisted first, the cable is not initially tensioned, the unbalanced bending moment is borne via the existing cable-stayed cable system, and the rear tensioned cable is used as a protective device. The aforementioned steps are repeated, and the two rear ends are symmetrically tensioned at the same time, which can ensure the reduction in tower deviation and the torsion caused by the single-side asymmetric hoisting problem (Figure 11)

4.2. Tower Deviation Analysis

The following experimental results can be obtained: the first seven sections of the experiment are constructed in the form of the unilateral installation and tightening of segment buckle cables, and the other side is the same. Section 8 adopts the construction method of lifting on both sides first, not tightening the cable, and pulling the cable on both sides at the same time after the symmetrical segment is installed. The following table shows the deviation data for the traditional hoisting of segments 2 and 6, and the deviation data for segment 8 using the new method. T1 is the measurement point at the bottom of the tower, T2 is the measurement point in the middle of the tower, and T3–T6 are the four measurement points at the top of the tower (Figure 12).
In Table 3 and Table 4, Δx is the longitudinal deviation of the bridge from the tower, Δy is the transverse deviation of the bridge from the tower, and Δz is the elevation change, indicating the change in the tower deviation on the hoisting side of the segment. Δx′ is the longitudinal deflection of the bridge towards the tower, Δy′ is the transverse deflection of the bridge towards the tower, and Δz′ is the elevation change, and the change in deflection of the mounting buckle tower on the other side of the symmetric segment. Measurements are made via total station. Table 3 and Table 4 list the traditional tensioning column deviation data.
Table 5 and Table 6 list the column deviation data of the eighth stage after adopting the new tensioning method.

5. New Methods of Optimization Data Analysis

Using data comparison, it can be found that the transverse deviation of the tower is insignificant, and most of the deviation is within 0.5 mm, so there is little scope for the description and calculation of the transverse deviation therein. The working conditions of A2, B2, and Section 6 are given in Figure 13, and the data pertaining to both the simulation and experiment are compared. To improve practicability, the maximum stress of the arch foot of the two methods corresponding to the section is listed (Figure 13).
It can be seen above that the method of the back cable can reduce the stress on some arch feet, and that on the eighth section, it can be reduced by about 25%. The following is a comparison of the actual and theoretical data of each section, and the last two charts allow the comparison of the data of the post-cable and traditional methods (Figure 14, Figure 15, Figure 16, Figure 17, Figure 18 and Figure 19).
It can be seen that the traditional method induces asymmetric column deviation control and torsion problems. The actual data indicate that T3–T6 is the control point at the top of the buckle tower, and the actual data differ greatly, so the effect of lifting the unilateral rear cable is poor.
The following new method is applied to Section 8: after hoisting two symmetrical segments, both sides are tensioned at the same time, and the data are compared with that collected when hoisting one side segment at a time(Figure 20 and Figure 21).
The comparison of the pictures shows that this method can actively and timeously correct the displacement deviation of the tower top and the torsion on the symmetric segment during the cable hoisting process, reducing the deviation. The maximum deviation of the tower pier can be controlled, in real time, to within the range of ± 0.5 mm.

6. Conclusions

To study the effect and operation of the new method of tower deflection control on the deflection of the buckle tower, and to apply it to the universality of similar bridge projects, the following conclusions can be drawn by establishing a 1:10 scale model:
(1)
The deflection of the buckle tower increases with the increase in the number of arch-rib lifting segments and the increase in pier elevation, from the bottom to the top of the tower;
(2)
The traditional way of controlling the deviation of the tower body is to pull a lot of steel wire and jack manually, which wastes a lot of materials and manpower. The new proposed method relies on the simultaneous tensioning technique, thereby greatly reducing the time cost, and obviating the need to adjust the offset;
(3)
After adopting the new method, the influence of adjusting the tower deviation on the structure members is rendered insignificant. This means that the adjustment has a significant controlling effect on the longitudinal displacement of the tower, and can reduce the stress on the arch foot; each section analyzed benefitted from a stress reduction of about 30 MPa compared with the previous method;
(4)
This method can actively and timeously correct the displacement deviation of the top of the tower and the torsion in the symmetric segment in the process of cable hoisting, reducing the deviation. The maximum deviation of the tower pier can be controlled, in real time, within the range of ±0.5 mm. Compared with the traditional methods and techniques, the results can provide a reference for the deviation control of the middle pier tower of similar types of bridge.

Author Contributions

X.D., methodology and finite element analysis, drawing and translation; D.Y., editing and modification. All authors have read and agreed to the published version of the manuscript as submitted.

Funding

This research received no external funding.

Data Availability Statement

The data are available on request only due to commercial restrictions.

Conflicts of Interest

The authors declare no conflict of interest.

References

  1. Yazhou, X. Structural Study of Arch Bridge With a Span of 600 m Part I: Trial Design. Appl. Mech. Mater. 2011, 138, 300–304. [Google Scholar]
  2. Zhang, F. Study on Filling Sequence of Long-Span Concrete-Filled Steel Tube Arch Ribs and Hydration Heat of Concrete in Pipes. Master’s Thesis, Chongqing Jiaotong University, Chongqing, China, 2020. [Google Scholar]
  3. Ma, Y. Application and development of concrete-filled steel tube arch bridge. Eng. Res. 2019, 4, 212–213. [Google Scholar]
  4. Wang, F.; Zheng, W.; Liu, H. Determination and Control of Alignment in Construction of CFST Arch Bridge. Technol. Highw. Transp. 2021, 37, 98–104+110. [Google Scholar]
  5. Gu, Y.; Li, Y.D.; Liu, S.Z. Research on Construction Control of Long-span CFST Arch Bridge. Appl. Mech. Mater. 2015, 777, 88–93. [Google Scholar] [CrossRef]
  6. Zhuo, X. Research on Construction Alignment Control of Main Girder of Half-Through Steel Box Arch Bridge Based on Grey Theory. J. Highw. Eng. 2021, 46, 26–32+67. [Google Scholar]
  7. Zheng, J.L.; Wang, J.J. Concrete-Filled Steel Tube Arch Bridges in China. Engineering 2017, 4, 143–155. [Google Scholar] [CrossRef]
  8. Chen, B.C.; Wang, T.L. Overview of Concrete Filled Steel Tube Arch Bridges in China. Pract. Period. Struct. Des. Constr. 2009, 14, 70–80. [Google Scholar] [CrossRef]
  9. Han, L.H.; Li, W.; Bjorhovde, R. Developments and advanced applications of concrete-filled steel tubular (CFST) structures: Members. J. Constr. Steel Res. 2014, 100, 211–228. [Google Scholar] [CrossRef]
  10. Gao, X.; Liu, L.J.; Yao, S.K.; Yang, J.W.; Li, Y. Commonly Encountered Damages in Cable Members of CFST Arch Bridge and Detection Methods. Key Eng. Mater. 2012, 619, 71–80. [Google Scholar] [CrossRef]
  11. Zhang, Z.-C.; Ye, G.-R.; Cheng, H.-Z. Calculation of SBC forces for concrete-filled steel tubular arch bridge with long span in process of lifting. J. Zhejiang Univ. Eng. Sci. 2004, 38. [Google Scholar] [CrossRef]
  12. Zhou, Q.; Zhou, J.T.; Ma, H.; Li, X.-G.; Zhang, L. Improved algorithm of cable force for one time cable tensioning on steel tube arch ribs with segmental hoisting. J. Traffic Transp. Eng. 2020, 20, 92–101. [Google Scholar]
  13. Zhou, Q.; Zhou, J.T.; Chen, J.W.; Feng, Y. Improved algorithm of cable force optimization of one—Time tensioning for arch bridge. J. Fuzhou Univ. Nat. Sci. Ed. 2019, 47, 412–416. [Google Scholar]
  14. Liang, D.; Zhao, K. Virtual Steel Pylon Segments Assembly Method Based on 3D Laser Scanning. Bridge Constr. 2019, 51, 62–71. [Google Scholar]
  15. Tian, W.; Liu, D. Closure Technique for Steel Truss Arch and Girder of the Second Hengqin Bridge in Zhuhai. World Bridges 2016, 44, 31–35. [Google Scholar]
  16. Wu, P.; Pan, R.; Guo, J. Study on Influences of Phlon Displacement on Arch Rib Elevation of Concrete Arch Bridge Using Cantilever Casting Method. J. Railw. Eng. Soc. 2020, 254, 154–158. [Google Scholar]
  17. Jiang, W.; Li, X. High Precision Calculation of Structural State of Main Cable during Cable Lifting Construction of Steel Tube Arch Bridge. J. China Foreign Highw. 2020, 252, 123–127. [Google Scholar]
  18. Lin, T.M.; Zhong, Q.S.; Li, S.R. Segmental catenary method of calculating the cable curve of suspension bridge. J. China Railw. Soc. 2003, 25, 87–91. [Google Scholar]
  19. Deng, J. Geometrical Analysis of Arch Rib Elevation Change Caused by Tower Deviation during Cable-Hoisting Construction. J. Chongqing Jiaotong Univ. Nat. Sci. 2009, 3, 505–508. [Google Scholar]
  20. Cheng, Z.G.; Bai, Y.H.; Liu, C.T. The Control of Tower Deviation on Arch Installation in Xiaohe Grand Bridge. Technol. Econ. Areas Commun. 2010, 3, 87–89. [Google Scholar]
  21. Yang, K.J.; Li, F.Q.; Zhang, Y.L. Research on the Design of Large Span Deck Steel Tube Concrete Arch Bridge. J. Railw. Eng. Soc. 2008, 25, 66–71. [Google Scholar]
  22. Deng, X.T.; Zeng, D.R.; Zhou, Y.Q. Finite Element Analysis of Stability of Cable-Hoisting Erection System of Long-Span Arch Bridge. J. Chongqing Jiaotong Univ. Nat. Sci. 2007, 26, 1–5. [Google Scholar]
  23. Shen, W.; Zhang, Y.Z.; Wen, L.U. Construction Control Method of Long-Span Steel Box Tied Arch Bridge. West. China Commun. Sci. Technol. 2009, 12, 85–89. [Google Scholar]
  24. Gao, Z. Traveling wave effect of multi-span through concrete-filled steel tubular arch bridge. J. Vibroengineering 2022, 24, 19. [Google Scholar] [CrossRef]
  25. Sheng, Z. Construction of Fastening Stay Tower at Pier No. 8 of Dashengguan Changjiang River Bridge in Nanjing. Bridge Constr. 2010, 2, 5–9. [Google Scholar]
  26. Zhu, Z.H.; Lun, Y.I.; Gao, Z.Y. Analysis of Mechanical Behavior and Study of Construction Control Measures of Triple Main Truss Structure of Dashengguan Changjiang River Bridge in Nanjing. Bridge Constr. 2009, 3, 28–32. [Google Scholar]
  27. Feng, R.; Zhao, H.; Tailei, C. Key Construction Techniques of Main Span Steel Truss Girder Flexible Arch of Guanhe Super-Long Bridge on Lianyungang-Yancheng Railway. Railw. Eng. 2017, 8, 47–49. [Google Scholar]
  28. John, J.S. Construction of the Hoover Dam Bypass. Concr. Int. 2010, 33, 30–35. [Google Scholar]
  29. Wei, J.; Chen, B. Application and research advancement of long span concrete arch bridges abroad. World Bridge 2009, 2, 4–8. [Google Scholar]
  30. Shi, W.Z.; Ko, J.M.; Zhao, C.Y.; Chen, L. A bridge structural health monitoring information system based on GIS and DBMS. In Proceedings of the International Society for Optics and Photonics, San Diego, CA, USA, May 2005. [Google Scholar]
  31. Yong, H.E.; Miao, Y.F.; Liu, H. Based on Beidou/GPS precise displacement monitoring technology in the application of the bridge monitoring. J. Yunnan Univ. Nat. Sci. Ed. 2016, 38, 35–39. [Google Scholar]
  32. Wu, J.-C.; Wang, Z.-C.; Shi, X.-Y. Application of Beidou Satellite Communication and Positioning Technology to the Field Geological Survey in Northwestern China. J. Geomech. 2012, 18, 282–287. [Google Scholar]
Figure 1. Layout of the Tianyun Bridge (unit: m).
Figure 1. Layout of the Tianyun Bridge (unit: m).
Buildings 13 02498 g001
Figure 2. Arch abutment (unit: mm).
Figure 2. Arch abutment (unit: mm).
Buildings 13 02498 g002
Figure 3. Intermediate pier (unit: mm).
Figure 3. Intermediate pier (unit: mm).
Buildings 13 02498 g003
Figure 4. Azimuth zoning scheme.
Figure 4. Azimuth zoning scheme.
Buildings 13 02498 g004
Figure 5. The second stage tower deviation (A2).
Figure 5. The second stage tower deviation (A2).
Buildings 13 02498 g005
Figure 6. The second stage tower deviation (B2).
Figure 6. The second stage tower deviation (B2).
Buildings 13 02498 g006
Figure 7. The sixth stage of tower deviation (D6).
Figure 7. The sixth stage of tower deviation (D6).
Buildings 13 02498 g007
Figure 8. The sixth stage of tower deviation (C6).
Figure 8. The sixth stage of tower deviation (C6).
Buildings 13 02498 g008
Figure 9. The eighth stage of tower deviation (A8).
Figure 9. The eighth stage of tower deviation (A8).
Buildings 13 02498 g009
Figure 10. The eighth stage of tower deviation (B8).
Figure 10. The eighth stage of tower deviation (B8).
Buildings 13 02498 g010
Figure 11. The method used to control tower deviation.
Figure 11. The method used to control tower deviation.
Buildings 13 02498 g011
Figure 12. Measuring points T1 to T6.
Figure 12. Measuring points T1 to T6.
Buildings 13 02498 g012
Figure 13. Comparison of arch-foot stress between the two methods.
Figure 13. Comparison of arch-foot stress between the two methods.
Buildings 13 02498 g013
Figure 14. Section 2 tower bias comparison.
Figure 14. Section 2 tower bias comparison.
Buildings 13 02498 g014
Figure 15. Section 2 tower bias comparison.
Figure 15. Section 2 tower bias comparison.
Buildings 13 02498 g015
Figure 16. Section 6 tower bias comparison.
Figure 16. Section 6 tower bias comparison.
Buildings 13 02498 g016
Figure 17. Section 6 tower bias comparison.
Figure 17. Section 6 tower bias comparison.
Buildings 13 02498 g017
Figure 18. Section 6 tower bias comparison.
Figure 18. Section 6 tower bias comparison.
Buildings 13 02498 g018
Figure 19. Section 6 tower bias comparison.
Figure 19. Section 6 tower bias comparison.
Buildings 13 02498 g019
Figure 20. The new method is compared with the traditional method (A8 + B8 sides).
Figure 20. The new method is compared with the traditional method (A8 + B8 sides).
Buildings 13 02498 g020
Figure 21. The new method is compared with the traditional method (C8 + D8 sides).
Figure 21. The new method is compared with the traditional method (C8 + D8 sides).
Buildings 13 02498 g021
Table 1. Model test similarity relationship.
Table 1. Model test similarity relationship.
Physical QuantityPrototypeModelModel Similarity Coefficient
LengthLpLm = Lp (1/n)1/10
Cross areaApAm = Ap·(Ep/Em) (1/n2) (1/m)1/100
Bending moment of inertiaIpIm = Ip·(Ep/Em) (1/n4) (1/m)1/10,000
Torque moment of inertiaJpJm = Jp·(Gp/Gm) (1/n4) (1/m)1/10,000
Modulus of elasticityEpEm1
stressσpσm = σp (Ep/Em)1
strainεpεm = εp1
Linear displacementδpδm = δp·(1/n)1/10
Angular displacementαpαm = αp1
counterweightWpWm = Wp (1/n2) (1/m)1/100
Concentrated loadFpFm = Fp (1/n2) 1/m)1/100
Shearing forceQpQm = Qp (1/n2) (1/m)1/100
reactionRpRm = Rp (1/n2)·(1/m)1/100
Bending momentMbpMbm = Mbp (1/n3) (1/m)1/1000
torqueMTpMTm = MTp (1/n3)·(1/m)1/1000
Note: In the table, n is the geometric scaling ratio (set to 10), and m denotes the scaling ratio of stress (set to 1).
Table 2. List of arch ring components (unit: mm) 30 September 2023.
Table 2. List of arch ring components (unit: mm) 30 September 2023.
PositionOriginal Bridge DimensionPrototype SizeModel SizeCompressive Stiffness RatioResistance to In-Plane Stiffness Ratio
Main chord 1φ1600 × 35φ80 × 1.7φ36 × 41.021.04
Main chord 2φ1600 × 32φ80 × 1.6φ35 × 41.21.11
Main chord 3φ1200 × 26φ70 × 1.3φ35 × 31.11.12
Web rod 1φ800 × 20φ40 × 1φ14 × 41.1/
Web rod 2φ600 × 16φ30 × 0.8φ15 × 31.2/
Parallel connection 1φ800 × 20φ40 × 1φ14 × 41.13/
Parallel connection 2φ800 × 22φ40 × 1.1φ12 × 31.15/
Parallel connection 3φ800 × 16φ40 × 0.8φ12 × 31.16/
Cross-brace 1φ800 × 22φ40 × 1.1φ14 × 41.13/
Cross-brace 2φ800 × 16φ35 × 1.1φ14 × 41.30/
Cross-brace 3φ700 × 22φ40 × 0.8φ12 × 31.09/
Cross-brace 4φ700 × 16φ35 × 0.8φ12 × 31.4/
Fork stay500 × 16/φ12 × 2.61.6/
Table 3. Section 2 tower deviation (unit: mm).
Table 3. Section 2 tower deviation (unit: mm).
ΔxΔyΔzΔxΔyΔz
T10.00060.00020.00040.00170.0003−0.0002
T20.00180.00060.00140.0010−0.00030.0002
T30.00480.00050.00210.0009−0.00050.0008
T40.00310.00080.00050.00000.0002−0.0002
T50.00210.00040.0005−0.0010−0.0001−0.0011
T60.00090.00020.0001−0.0026−0.0003−0.0004
Table 4. Section 6 tower deviation (unit: mm).
Table 4. Section 6 tower deviation (unit: mm).
ΔxΔyΔzΔx′Δy′Δz′
T1−0.00010.0003−0.00040.00030.0002−0.0002
T2−0.0005−0.0003−0.00030.00050.00060.0002
T3−0.0020−0.00050.00060.00090.00050.0008
T4−0.00250.0002−0.00010.00100.0008−0.0002
T5−0.0027−0.0001−0.00120.00140.0004−0.0011
T6−0.0047−0.0003−0.00070.00160.0002−0.0004
Table 5. Section 8 tower deviation (unit: mm).
Table 5. Section 8 tower deviation (unit: mm).
ΔxΔyΔzΔx′Δy′Δz′
T1−0.00020.0003−0.00040.00030.00020.0002
T2−0.0010−0.0009−0.00030.0005−0.00030.0004
T3−0.0042−0.00060.00060.00090.00080.0006
T4−0.0037−0.0005−0.00010.0010−0.0002−0.0002
T5−0.00300.0002−0.00120.00100.0009−0.0009
T6−0.0025−0.0008−0.00070.00110.0008−0.0004
Table 6. Section 8 tower deviation (unit: mm).
Table 6. Section 8 tower deviation (unit: mm).
ΔxΔyΔzΔx′Δy′Δz′
T10.00030.00020.0002−0.0002−0.0002−0.0002
T20.00060.00050.0005−0.00040.00030.0002
T30.00110.00040.0016−0.0007−0.00040.0008
T40.00090.00050.0006−0.0006−0.0002−0.0002
T50.00070.00060.0001−0.00070.0002−0.0011
T60.00050.00030.0000−0.00060.0005−0.0004
Disclaimer/Publisher’s Note: The statements, opinions and data contained in all publications are solely those of the individual author(s) and contributor(s) and not of MDPI and/or the editor(s). MDPI and/or the editor(s) disclaim responsibility for any injury to people or property resulting from any ideas, methods, instructions or products referred to in the content.

Share and Cite

MDPI and ACS Style

Dong, X.; Ye, D. A New Method for Correcting the Deviation of a Middle Pier Tower of a Long-Span Intermediate Arch Bridge. Buildings 2023, 13, 2498. https://doi.org/10.3390/buildings13102498

AMA Style

Dong X, Ye D. A New Method for Correcting the Deviation of a Middle Pier Tower of a Long-Span Intermediate Arch Bridge. Buildings. 2023; 13(10):2498. https://doi.org/10.3390/buildings13102498

Chicago/Turabian Style

Dong, Xiaojin, and Dan Ye. 2023. "A New Method for Correcting the Deviation of a Middle Pier Tower of a Long-Span Intermediate Arch Bridge" Buildings 13, no. 10: 2498. https://doi.org/10.3390/buildings13102498

Note that from the first issue of 2016, this journal uses article numbers instead of page numbers. See further details here.

Article Metrics

Back to TopTop