Next Article in Journal
Open-Phase Fault Tolerance Techniques of Five-Phase Dual-Rotor Permanent Magnet Synchronous Motor
Next Article in Special Issue
Comparing World Economic and Net Energy Metrics, Part 1: Single Technology and Commodity Perspective
Previous Article in Journal
Sanitation and Analysis of Operation Data in Energy Systems
Previous Article in Special Issue
Are Shocks to Wood Fuel Production Permanent? Evidence from the EU
 
 
Font Type:
Arial Georgia Verdana
Font Size:
Aa Aa Aa
Line Spacing:
Column Width:
Background:
Article

Economic Evaluation on Bio-Synthetic Natural Gas Production Integrated in a Thermomechanical Pulp Mill

FSCN—Fibre Science and Communication Network, Mid Sweden University, Sundsvall SE-85170, Sweden
*
Author to whom correspondence should be addressed.
Energies 2015, 8(11), 12795-12809; https://doi.org/10.3390/en81112343
Submission received: 13 August 2015 / Revised: 30 October 2015 / Accepted: 2 November 2015 / Published: 12 November 2015
(This article belongs to the Special Issue Economics of Bioenergy 2015)

Abstract

:
In this study, biorefinery as a concept is applied to thermomechanical pulp (TMP)-based paper production to evaluate the possibility of co-production of synthetic natural gas (SNG), electricity and district heating in addition to mechanical pulp and paper. The combined heat and power plant (CHP) associated to TMP is replaced by a biomass-to-SNG (BtSNG) plant. Implementing BtSNG in a mechanical pulp production line might improve the profitability of a TMP mill and also help to commercialize the BtSNG technology by taking into account of some key issues such as biomass availability, heat utilization, etc. A TMP + BtSNG mathematical model is developed with ASPEN Plus. The model prediction shows that the scale of the TMP + BtSNG mill and SNG price are two strong factors for the implementation of BtSNG in a TMP mill. A BtSNG plant associated to a TMP mill should be built at a scale above 100 MW of biomass thermal input. For the case of Swedish economic condition, commercialization of SNG production as a transport biofuel has not matured yet. Political instruments to support commercialization of transport biofuel are necessary.

1. Introduction

The possibility of producing transport fuels from biomass and wastes has become a more and more important issue with regard to the global challenges of energy security and climate change. The present transportation biofuels on the market are produced mainly from food crops, referred to as the 1st generation biofuels, which are not encouraged any longer in Europe Union (EU) after the EU directive on the biofuels sustainability criteria in 2009. From the viewpoint of economics, the environment, land use, water use, chemical fertilizer use, etc., however, there is a strong preference for the second generation biofuels that are produced using woody, grassy materials as well as agricultural residues, municipal wastes and industrial wastes as feedstocks. Thus, the production of synthetic transport fuels such as methanol, ethanol, dimethyl ether, Fischer-Tropsch fuel and synthetic natural gas (SNG) via gasification and synthesis is promising [1]. Production of these fuels from coal and natural gas has been successfully commercialized, e.g., by Sasol and Mobil [2]. For biomass, however, the technology has not been established, mainly due to the high production cost for limited scale biomass-based plants.
Among the abovementioned fuels, bio-SNG can be produced easily since the once-through methanation conversion efficiency is high even under moderate pressure and temperature conditions and a sophisticated upgrading of products is not needed. Thus, biomass to SNG (BtSNG) can be realized commercially with a medium scale of around 100 MW in comparison to the large scale of thousands of MW in fossil fuel plants.
For an extremely small scale, the German company, Agnion, offers bio-SNG plants based on a heat-pipe reformer concept with a capacity of approximate 3 MW bio-SNG [3]. The isothermal fluidized bed methanation developed at the Paul Scherrer Institute and commercialized by Clean Technology Universe was demonstrated with a scale of 1 MW in Güssing in 2009. A larger scale demonstration plant of 20 MW bio-SNG output has been put into operation at the end of 2014 in Gothenburg as the GoBiGas project, which is scheduled to scale up to 100 MW bio-SNG plant in 2016. A bio-SNG plant of 200 MW is planned in the E.ON Bio2G project. Depending on technology, scale, and energy prices, the most economic configuration may provide a net SNG yield of 66% to 75% from wood (based on lower heating value (LHV) of the dry substance). The poly-generation of fuel, heat, and power allows for a total useful energy yield ranging from 71% to 91% [4]. Bio-SNG can be used in a variety of applications:
  • Grid injection;
  • Vehicle fuel;
  • Chemical feedstock;
  • Fuel for electricity or heat production.
In Sweden, Germany and many other countries, biogas produced from waste treatment through digestion has been used in the market as a vehicle fuel. The scale has expanded rapidly in recent years. This provides an excellent infrastructure and market opportunity for bio-SNG production as a transport fuel.
High yield pulp (HYP) is the denotation for processes such as stone groundwood (SGW), pressure groundwood (PGW), thermomechanical pulp (TMP) and chemothermomechanical pulp (CTMP). The wood to final pulp yield ranges from 85% to 98% which is much higher than typical chemical pulp processes that normally have a yield of about 50%. TMP, SGW, PGW and recycled paper-based pulp (deinked pulp—DIP) are mostly used in printing papers, while CTMP is used in many different paper and packaging grades (printing, paperboard, tissue, fluff). The drawback with HYP processes is that they are the most electrical energy-intensive processes in the pulp & paper industry, with an electricity consumption of 2–3 MWh/t. CTMP-process electricity consumption ranges from 0.7 MWh/t to 2 MWh/t, depending on the final product. It should however be emphasized that up to about 70% of the electricity consumption is regained as low-pressure steam that is used for drying of the paper products. To substantially reduce specific electricity consumption (SEC) while maintaining pulp quality is therefore the most important issue for the high-yield pulp and paper industry [5]. The Fibre Science and Communication Network (FSCN) at Mid Sweden University, together with Scandinavian forest and pulp & paper companies and research institutes, is running a large research program with the goal of showing how to design the TMP and CTMP production lines of the future to reduce SEC by 50%. Today, some logging residues (branches and tree tops) are utilized as a source of bioenergy, but the major part of the logging residues remains in the forest in many countries, e.g., Sweden. The logging residues represent about 30% of the biomass of the felled trees. Most of the bark (>10% of the log biomass) follows the logs to the pulp- or sawmills to be used in combined heat and power plants (CHPs). Due to fiber morphology reasons about 10% of the fiber material in the final pulp has a negative influence on the final product properties [6]. The possibilities of utilizing not only bark, but also branches and tops as well as the pulp fibers with negative impact on paper properties as a source of bioenergy has not been evaluated. The total potential amount of biomass available is thus about 0.66 ton per ton of pulp and 0.84 ton if 10% low quality pulp fibers are also used (normally, only the bark, shavings, and biosludge are utilized in present bark boilers of CHP systems of TMP mills).
A previous study investigated the profitability of a TMP mill integrated with a biomass integrated gasification combined cycle (BIGCC) for electricity generation [7]. In the present study, the feasibility of biomass gasification-based technology to produce CH4 in a TMP mill is evaluated and compared with TMP + BIGCC in terms of the technical and economic aspects.
A TMP + BtSNG mathematical model is developed with ASPEN Plus. By means of modeling, three cases are studied:
1)
Scaling of the TMP + BtSNG mill;
2)
Adding the reject fibres in the gasifier;
3)
Decreasing the TMP-specific electricity consumption (SEC) by up to 50%.
The profitability of the TMP + BtSNG mill is analyzed in comparison with a previously studied TMP + BIGCC mill.

2. Process Design and Simulation

2.1. Thermomechanical Pulp (TMP) + Paper Mill (PM)

A paper mill (PM) with a TMP process has a very high wood-to-pulp/wood-to-paper yield (>95%), but consumes a large amount of electricity (about 2.5 MWh per ton of pulp in TMP and 0.75 MWh per ton of paper in PM as given in Table 1).
Table 1. Outline of a thermomechanical pulp (TMP) and paper mill (PM) [8].
Table 1. Outline of a thermomechanical pulp (TMP) and paper mill (PM) [8].
Mass/energyTMPPM
Yield230,000 t/year250,000 t/year
Pulpwood with Bark250,000 t/year-
Pulpwood220,000 t/year-
Biomass Residues-3.9 a MWh/bdt pulp
Electricityconsumption2.5 MWh/bdt pulp0.75 MWh/bdt pulp
Steamproduction1.2 MWh/bdt pulp-
consumption0.03 MWh/bdt pulp1.38 b MWh/bdt pulp
a including logging residues, bark, bio-sludge and reject fibres; see Figure 1; b in: 1.38 (2.0 t/bdt pulp) = 1.32 (2.5 bar) + 0.06 (100 bar); out: 2.0 t/bdt pulp = 0.2 (to the air) + 1.8 (condensed).
Figure 1. Available biomass residues in a TMP mill.
Figure 1. Available biomass residues in a TMP mill.
Energies 08 12343 g001
Since a TMP process is normally integrated with paper production, the electricity consumed in the refining process is simultaneously utilized to obtain hot water and steam for paper drying. Some of the input data to this model are from a TMP + PM mill of Holmen Paper in Hallsta [8], as presented in Table 1.
Biomass residues from a TMP + PM mill are traditionally utilized through a CHP plant to supply the mill electricity and steam. The original CHP plant is intended to be replaced by a BtSNG plant in the model. Figure 1 illustrates the source of the biomass residues available for the gasification plant associated to a TMP mill. The available biomass residues are significant and include:
1)
Logging residues, amounting to 30% of the tree;
2)
Bark, 12% of the stem;
3)
Bio-sludge, 2% of the pulpwood; and
4)
Reject fibers, 10% of the pulp.
As a result, 0.84 ton of biomass residues are available from the production of each ton of pulp. Additional biomass (including peat) can be gained from other applications, e.g., the production of chemical pulp, which are not taken into account in the economic evaluation of this work.

2.2. Biomass-to-Synthetic Natural Gas (BtSNG)

Before setting up a mathematic model, a BtSNG process flow diagram is designed as shown in Figure 2. The process is established with five steps: biomass pretreatment, gasification, syngas cleaning and conditioning, SNG synthesis, and separation and purification. This system includes a steam turbine system to utilize the waste heat from BtSNG to generate electricity and steam for the use in a TMP + PM mill.
Figure 2. Model of biomass-to-synthetic natural gas (BtSNG) with a fluidized-bed SNG synthesis system.
Figure 2. Model of biomass-to-synthetic natural gas (BtSNG) with a fluidized-bed SNG synthesis system.
Energies 08 12343 g002

2.2.1. Biomass Pretreatment

Fresh biomass has a high moisture content of up to 50 wt%, is inhomogeneous in shape and size, and needs pretreatment before being fed to a gasifier. The pretreatment process is illustrated in Figure 2. Biomass chips are weighed and screened. Metal debris is removed through a magnetic separator. Particles larger than 10 mm are conveyed to a hammer mill for further size reduction. Wet biomass is dried by utilizing the waste heat from the TMP and BtSNG plants. Before being pumped to the atmosphere, the exhausted flue gas passes through a cyclone to separate some particulates. The temperature of the stack flue gas is controlled.

2.2.2. Gasification

In this study, a dual fluidized bed gasifier (DFBG), so called indirect gasifier, is chosen for biomass gasification. It consists of a bubbling fluidized bed gasifier and a circulating fluidized bed combustor. Production of high-quality syngas from biomass gasification in DFBGs has made a significant progress in R&D and technology demonstration. A small and medium (S&M) scale bio-automotive fuel plant close to the feedstock resources is preferable as biomass feedstock is quite sparse and has relatively low density, low heating value and high moisture content. This requires a simple, reliable and cost-effective production of clean and good quality syngas. Indirect DFBGs, with steam as the gasification agent, produces a syngas of high H2 and CO content with 12–20 MJ/Nm3 heating value. Good quality syngas from DFBGs can be obtained by optimized design and operation of the gasifier, by the use of active catalytic bed materials including those for internal reforming of tars, and finally by a downstream cleaning process. Olivine is a suitable bed material with enough resistance to attrition and moderate tar cracking activity. The DFBG gasification opens a possibility to produce syngas suitable for methanation at an S&M scale. However, in order to produce bio-SNG, extensive gas cleaning is needed.

2.2.3. Gas Cleaning

Syngas cleaning is the key issue for commercialization of biomass gasification technology, and has been reviewed by many researchers [9]. Raw syngas contains various impurities such as tars, sulfurous and nitrogenous compounds, alkali metal species, ash, and char. These impurities are potential threats to methanation catalysts. The cleaning process designed in the model is illustrated in Figure 2.
Firstly, the syngas passes through a high temperature particle filter, and the tars in the syngas are cracked down by a monolith Ni catalytic reformer before syngas temperature drops. The tar reformer operates isothermally at 710–890 °C [10]. The reforming unit consists of a catalytic reformer and a catalyst regenerator. Energy for endothermic reforming is transferred from the circulating catalytic bed material that acts as heat carrier as well. The reformed syngas flows through a cyclone and is cooled to 150 °C, while the flue gas from the regenerator is sent to a biomass drier through another cyclone. The tars can also be stripped of vegetable oil, and the spent scrubber liquid saturated with tar and condensate is vaporized and recycled to the combustor coupled with the gasifier. The syngas is further cleaned via water scrubbing, and impurities like particulates, residual tars and ammonia are further reduced. Subsequently, the syngas is compressed to the pressure of methanation reactor leaving NH3 and H2O condensed. Afterwards, acid gases (CO2 and H2S) removal is carried out in an amine-based absorption (MEA) system. A CO-shift unit is used to adjust H2/CO molar ratio. The investment and operating cost for the gas cleaning is discouraging, especially if one moves to the smaller plant sizes.

2.2.4. Methanation

Methanation can be either carried out in a series of adiabatic fixed bed reactors with inter-cooling and optional product recycle, or in a single fluidized bed reactor under isothermal conditions [11]. Ni-based catalysts are commonly used. Methanation is highly exothermic [12,13]. The temperature should be generally kept low to favor the equilibrium. It should be considered that the temperature is limited by the catalyst activation and carbon deposition problems. The operation is also limited by catalyst sintering problems at higher temperatures. The fixed bed methanation is operated at temperature around 650 °C, whereas the fluidized bed methanation around 300 °C.
A higher pressure is favorable for CH4 formation. The operation at a higher pressure increases the methanation conversion efficiency and reduces the amount of catalyst required. For adiabatic fixed bed methanation, the pressure should be high, about 10 bar, corresponding to the high temperature. For fluidized bed methanation, on the other hand, the pressure should be low, about 4 bar, corresponding to its low temperature. A high conversion efficiency of methanation can also be achieved even at atmospheric pressures. A compression stage prior to the methanation stage ensures the necessary pressure for final SNG delivery to a local distribution network, otherwise, additional compression of final SNG is needed [11,13].
Methanation Reactions [14]:
CO   +   3 H 2     CH 4   +   H 2 O ,   Δ H 298 o = 206   kJ / mol
CO 2   +   4 H 2     CH 4   +   2 H 2 O ,   Δ H 298 o = 165   kJ / mol
C   +   2 H 2     CH 4 ,   Δ H 298 o =   75   kJ / mol
2 CO     C   +   CO 2 ,   Δ H 298 o = 172   kJ / mol
Water-gas shift reaction:
CO   +   H 2 O     CO 2   +   H 2 ,   Δ H 298 o =   41   kJ / mol
Fluidized bed methanation is a key technology to realize cost-effective bio-SNG production at a medium scale [3,4]. This reactor type is able to handle syngas with a wide range of CO/H2 ratios, from 1 to 5 if water addition is optimized. The advantages of a fluidized bed methanation reactor compared to the fixed bed methanation reactors are the isothermal operation, the easy control, the possibility for the in-situ water gas shift reaction to adjust the H2/CO ratio and the low risk of catalyst deactivation due to recirculation of the catalyst particles through the beds. There is a good synergy between DFBG and fluidized bed methanation as both have a moderate operation condition and make production cost reduction possible. Since the methanation reaction equilibrium is reached in both fluidized and fixed bed reactors, the conversion efficiency to SNG is yet expected to be the same, and only the combined heat and power production might differ due to the respective dissimilar heat transfer profiles of the heat exchangers [4]. In present work, the fluidized bed methanation reactor is chosen for modeling BtSNG.

2.2.5. Upgrading

The upgrading of bio-SNG is simple compared to other synthetic fuels. A minor part component of CO2 in the product gas needs to be removed. MEA, pressure swing adsorption (PSA) and physical absorption with Selexol are suitable for CO2-removal either up- or downstream of methanation, whereas membranes can only be applied downstream due to the fast permeation of H2. Downstream to these CO2-removal options, a final polysulfone membrane for H2 removal and recycling to the CH4 synthesis reactor has further proven useful to reach the required grid quality of 96 mol. % CH4 [4].

2.3. Thermomechanical Pulp (TMP) + Biomass Integrated Gasification Combined Cycle (BIGCC)

The techno-economic analysis of TMP + BIGCC has been studied previously [7]. Coal-based IGCC technology has been effectively commercialized. Biomass-based IGCC technology, however, is at a pre-commercialization stage, with syngas cleaning as a key issue. In the previous study, DFBG was chosen for biomass gasification. The original CHP plant was replaced by a BIGCC plant.
The results from the TMP + BIGCC study indicated that the TMP + PM electricity consumption cannot be fully made up by the electricity supply from a BIGCC plant with the amount of biomass feedstock corresponding to the amount of pulpwood, even if the TMP SEC goes down by 50%. But the gap becomes fairly small, and much smaller in comparison with the case of a CHP plant. Lower TMP SEC leads to higher economic profit in both the net revenue (NR) and the internal return rate (IRR). The profit of a TMP mill is ranked as: TMP + BIGCC > TMP + CHP > TMP + Boiler.

2.4. Simulation with ASPEN Plus

ASPEN Plus is an excellent modeling tool which is versatile and relatively easy to use. It can be used to model complicated chemical engineering systems. It includes many model blocks to simulate various unit operations. If more sophisticated block ability is required, additional information will be added into the block in a form of FORTRAN subroutines, or an entirely new user block can be created.
The BtSNG model is set up with several ASPEN Plus modules. Each module simulates a unit process. The input data were collected from a variety of sources including experimental and literature data as given in Table 2. The overall mass and energy balance of the integrated mill is examined.
Table 2. Model input data [4,7,11,15].
Table 2. Model input data [4,7,11,15].
Lower heating value (LHV) biomass(MJ/kg, daf)18
EfficiencyGasification(%)80
Combustion99
Boiler75
DryingFlue gas inlet(°C)550
Outlet120
Gasification-(°C)850–900
SyngasYield(Nm3/kg daf biomass)1.1
Composition(vol%)H2 37.5, CO 35.0, CO2 15.0, CH4 8.0, C2H4 0.5 and N2 4.0
LHV(MJ/kg)13.0
MethanationFB(°C)300
(bar)5–15
Purification
(pressure swing adsorption)
CO2 removal(%)95–99
SNG recovery(%)95–99
Adsorption pressure(bar)5.5
SteamTo turbine in PM(°C)500
(bar)60
(bar)2.5
The accessed equations and data were packaged in a specific Property Method set in ASPEN Plus. The involved substances and operation conditions are crucial in choosing a proper Property Method. For gas phase processes, the Peng-Robinson equation of state with Boston-Mathias modification was applied [11,13]. For the H&P system, the Property Method STEAM-TA was employed [7,16]. For the units involving electrolytes, the electrolyte non-random two liquid model, ELECNRTL, in ASPEN Plus was applied.
The gasifier and combustor were modeled with the module “RGibbs” which executes equilibria calculations by Gibbs free energy minimization. When a system does not reach a complete equilibrium state, “RGibbs” can also be used by additionally specifying an extent of equilibrium.
The modeling of the shift reactor is done with an adiabatic Gibbs reactor where CH4 is considered inert and therefore does not take part in the steam reforming [13]. The assumption is considered valid since the shift reactor utilizes a different type of catalyst than the methanation reactor and therefore no methanation or steam reforming should occur in the reactor.
An RGibbs module was used for methanation simulation [11,17]. A temperature approach to equilibrium measure was adopted for the composition calculations in order to account for the deviation from the thermodynamic equilibrium in a real reactor.
A compressor or a turbine was simulated with a module “Compr” which can calculate the power consumed or produced. The heat exchanger was simulated with the module “Heatx”, the pump with the module “Pump”, and the flow splitter “FSplit”.
The ASPEN Plus function block “Design Spec” and in-built “Calculator” were applied for parameters adjustment and process control. In essence, it is a multi-objective optimum design method adopted. This model is based on the following assumptions [3,4,13,18,19]:
  • Biomass devolatilization is instantaneous in comparison with the char gasification;
  • The methanation reaction and shift reaction go fast so that the thermodynamic equilibrium is reached;
  • The overall CO conversion could approach to 98%;
  • 98% steam is estimated to be condensed;
  • The energy required for CO2 removal is considered to be 4.0 MJ/kg CO2;
  • Biomass to SNG energy conversion efficiency = 63%;
  • The overall energy conversion efficiency >90%;
  • CH4 concentration >95%;
  • The CH4 losses are about 2.0%–4.0%.

2.5. Economic Evaluation

The economic profitability of TMP + BtSNG is evaluated in terms of NR (after subtracting the depreciation) and IRR. IRR is also called the discounted cash flow rate of return or the rate of return. IRR disregards the absolute amount of money to be gained, and is an indicator of the efficiency, quality, or yield of an investment. An investment is considered acceptable if its IRR is higher than an established minimum acceptable IRR, 0.1 for instance. Generally, the higher is the IRR and the better the investment.
Table 3. Data for economic analysis [3,7,11,19,20]. BIGCC: biomass integrated gasification combined cycle; DDB: Double-Declining Balance method.
Table 3. Data for economic analysis [3,7,11,19,20]. BIGCC: biomass integrated gasification combined cycle; DDB: Double-Declining Balance method.
Operation time8000 h/year
Power generation efficiency45% (calculated in the model for BIGCC)
Specific capital investment3470 €/kWbio-SNG (BtSNG)
2300 €/kWel (BIGCC)
1920 €/tpy (TMP+PM)
Pulpwood20 €/MWh
Biomass to BtSNG15 €/MWh (the logging residues)
0 €/MWh (the TMP residues)
Operation & maintenance cost0.065° the total capital investment
Operators12 p./shift
Operator salary60,000 €/year
Paper710 €/t
Bio-SNG price60 €/MWh
Electricity price40 €/MWh
Electricity certificate credit20 €/MWh
Heat60 €/MWh
Plant lifespan30 years
Discounted payback period10 years
Annual depreciationThe first 10 yearsDDB (factor 1.5)
The next 20 yearsStraight-line Depreciation
Profit tax rate0
Discount factor0.1
For a TMP + PM mill, its capital investment is about 1920 €/tpy [20] for a given paper production capacity as seen in Table 3. The specific capital investment for BIGCC is 2300 €/kWel [21], and for BtSNG 3470 €/kWbio-SNG [19]. The prices for some facilities are indicated in the literature [10,22]. The operation and maintenance cost accounts for 6.5% of the capital investment of a combined TMP + BtSNG mill. Electricity is purchased at about 40 €/MWh. An electricity certificate credit of 20 €/MWh is taken into account. The price of pulpwood is 20 €/MWh. The discounted payback period is set as 10 years. The available biomass residues from a TMP mill are free of charge. The overall cost for the logging residues is 15 €/MWh in synergy with pulpwood harvesting. The heat is sold at 60 €/MWh for district heating (DH). The plant lifespan is anticipated to be 30 years. In sensitivity analysis, the bio-SNG is priced at 60 or 120 €/MWh, and the pulpwood at 20 €/MWh or 40 €/MWh. The other values are unchanged. Two depreciation methods are adopted: for the first 10 years the Double-Declining Balance method (DDB), and for the next years the Straight-line Depreciation method.

3. Results and Discussion

3.1. Implementation of Biomass-to-Synthetic Natural Gas (BtSNG) in a Thermomechanical Pulp (TMP) Mill

The TMP + BtSNG block flow diagram with an outline of mass and energy input and output is shown in Figure 3. About 100 MW of biomass residues including bark, bio-sludge, reject fibers from TMP and logging residues from pulpwood harvesting in forest are available for bio-SNG production in the TMP + PM mill with a paper production capacity of 250,000 t/year, higher than the pulp used due to addition of chemicals. 63 MW of bio-SNG can be produced, as the bio-SNG yield of BtSNG is estimated to be 63%. The remaining energy of 37 MW of biomass feedstock is carried by flue gas from the combustor, the product gas from the gasifier, the cooling medium from methanation, etc. in the form of heat at different temperatures. This heat energy is recovered to generate 31 MW steam going to the steam cycle in the H&P centre with 6 MW heat loss. The H&P centre subsequently supplies TMP + PM with 9.5 MW steam and DH with 4.5 MW low temperature heat. The steam cycle in the H&P centre has a generation efficiency of 20% and produces 6 MW electricity to meet the demand of BtSNG for the compression of syngas and bio-SNG, syngas cleaning, CO2 removal, gasifier operation etc. No excess electricity is available from the TMP + PM mill. On the other hand, the H&P centre can supply TMP + PM with enough steam, 9.5 MW, and 4.5 MW low grade heat energy is recovered as DH. As a result, the H&P centre has a total efficiency of about 65%, and BtSNG has an overall efficiency of 83%.
Figure 3. Flowsheet of the TMP + BtSNG process with mass and energy inputs and outputs [23].
Figure 3. Flowsheet of the TMP + BtSNG process with mass and energy inputs and outputs [23].
Energies 08 12343 g003
Compared to BIGCC, as seen in Figure 4, BtSNG gives almost double yield in terms of energy content, which results in much lower waste heat (WH) and DH.
Figure 4. Comparison of BtSNG with BIGCC regarding their outputs in energy content.
Figure 4. Comparison of BtSNG with BIGCC regarding their outputs in energy content.
Energies 08 12343 g004
The energy balance over the TMP + BtSNG mill is studied by applying the model, in comparison with other two cases of TMP + BIGCC and TMP+ Boiler studied previously [7], as seen in Figure 5.
For the TMP + PM mill studied, the TMP SEC is 2.5 MWh/bdt pulp, the PM SEC is 0.75 MWh/bdt pulp, and the steam consumption in the PM is 1.38 MWh/bdt pulp (see Table 1). The total steam demand is kept constant because of the constant paper throughput, and is provided from the steam energy recovered mainly from the TMP refining process and also from the BtSNG process to a minor degree. The enhancement of refining efficiency lowers the steam yield from TMP. Removal of the reject fibers makes the TMP more energy-efficient, i.e., the TMP SEC is reduced, and the steam yield from TMP is also reduced. A decrease in the steam generation from TMP is compensated for from the BtSNG plant so that the bio-SNG yield may be reduced. The model is designed to ensure that the steam consumption is sufficiently satisfied, as the results indicate in Figure 5. The remaining low-grade energy is utilized in DH. The heat energy for DH is provided from both TMP and BtSNG.
Figure 5. Energy balance when SNG or electricity is produced in a TMP mill [23].
Figure 5. Energy balance when SNG or electricity is produced in a TMP mill [23].
Energies 08 12343 g005
In the Boiler case, which is common for present TMP mills, the TMP biomass residues such as bark, reject fibers are burned to produce the steam needed by PM. No poly-generation is considered by utilizing the large amount of logging residues as seen in Figure 5.
Compared with the case of BIGCC, BtSNG1 gives almost double product yield in energy content and much less DH and WH, so that the overall energy efficiency is high, but more electricity will need to be purchased.
In the case of BtSNG2 when the reduction of SEC (SECR) is raised from 0% to 30%, the steam generated from TMP refining is reduced, and more steam production from BtSNG is required. The steam demand exceeds the steam provided by BtSNG under normal operation condition of maximizing bio-SNG production. Thus a part of syngas will be burned to provide steam, which gives rise to a lower bio-SNG yield.
In the case of BtSNG3 when the SECR is raised to 50% by 10% fibre rejection, the bio-SNG yield is increased back to the level of the BtSNG1 case in spite of more syngas going to steam production. This is attributed to the 10% reject fibers leading to twofold impacts: (1) direct addition of 10% reject fibers as feedstock to BtSNG and (2) indirect addition of total biomass residues to the gasifier. The usable biomass is 3.1 MWh/bdt pulp including the logging residues, bark, and bio-sludge, and is 3.9 MWh/bdt pulp further including the 10% reject fibers. The paper yield will be kept by adding more pulpwood though the reject fibers are moved out.

3.2. Economic of Scale

The above analysis of energy balance over the TMP + BtSNG mill is based on a typical scale of TMP + PM mills with a paper production capacity of 250,000 t/year. The corresponding scale of the BtSNG plant is about 100 MW of biomass thermal input as seen in Figure 1 and Figure 3. The scale of the BtSNG will be taken to represent the whole scale of the TMP + BtSNG mill for economic analysis as shown in Figure 6.
As seen in Figure 6a, the bio-SNG production per ton of pulp holds constant against the scale, which indicates a linear relationship between the bio-SNG production and the TMP pulp output. The steam produced from the H&P centre associated to the BtSNG plant is fairly limited in comparison with the BIGCC plant, but still can meet the demand of the TMP + PM mill as shown in Figure 6b. Very little heat energy is available for DH, which can also be observed from Figure 5.
Figure 6. Effect of the BtSNG plant scale as the biomass thermal input.
Figure 6. Effect of the BtSNG plant scale as the biomass thermal input.
Energies 08 12343 g006
The economic profitability is sensitive to both the SNG price and the pulpwood price as seen in Figure 6c,d. When the SNG price is doubled, the IRR increases from about 2% to about 16%. When the pulpwood price is doubled, the IRR decreases from about 2% down to about −13%. The NR and IRR increase with the plant scale and level off after 100 MW.
Compared to the results of the case of TMP + BIGCC, represented by the dashed curves in Figure 6c,d, the NR and IRR of TMP + BtSNG are much lower. This is attributed to three reasons: (1) the specific investment cost is much higher for BtSNG; (2) the electricity certificate instrument in Sweden has added a credit to the electricity production; and (3) much more DH is produced by BIGCC, and DH has a price unusually high (higher than electricity used in industries in Sweden, which has a very low tax comparing to heavy tax for the electricity used in the domestic sector such as DH system).
In summary, plant scale and SNG price are two strong factors for the implementation of BtSNG in a TMP mill. A BtSNG plant associated to a TMP mill should be built at a scale above 100 MW in biomass thermal input. Political instruments to support commercialization of transport biofuel are necessary.

3.3. Reject Fibers to Gasifier

Usually in TMP mills, up to about 10 wt% of the pulp fibers have properties that are not good enough to remain in the final product, and they may be removed as reject fibers. They can be utilized as feedstock to biomass gasifiers. 20% TMP SECR should be possible when taking out the fibers with respect to final paper product properties [6].
As seen in Figure 7a, with the amount of reject fibers, the bio-SNG yield per ton of pulp clearly increases for two reasons: (1) the reject fibers are directly added in the gasifer; and (2) the usable biomass residues increase as the product paper output is kept constant. Corresponding to the increase in feedstock, the amount of steam and heat produced from BtSNG increases as well. At the same time, the steam demand by the TMP + PM mill also increases since the low quality fibers rejection possibly leads to a lower TMP SEC and less steam supply from TMP to PM. Thus, the steam demand by TMP + PM is well balanced with the steam supply from BtSNG.
Figure 7. Effect of adding reject fibres.
Figure 7. Effect of adding reject fibres.
Energies 08 12343 g007
Figure 7c,d shows that the NR and the IRR values increase with the amount of the reject fibers. This can be explained by several factors: (1) more SNG is generated as more reject fibers are added; (2) the TMP SEC is cut down; (3) the paper yield is held by supplementing pulpwood. Compared to the case of TMP + BIGCC, TMP + BtSNG shows a much lower profitability for the same reasons mentioned above.

3.4. Improved Electric Energy Efficiency of Thermomechanical Pulp (TMP)

TMP SEC is a key factor in the high cost pulp production. A 50% SECR is targeted. The SECR is indicated by the dashed line in Figure 8a. With SECR, less steam can be supplied from TMP. BtSNG must make up the balance (Figure 8b). The availability of biomass for the conversion from biomass to SNG will therefore be lowered (Figure 8a), and the steam provided from BtSNG to TMP + PM increases as shown in Figure 8b. In some TMP + PM mills, a backup boiler is specially used to supply steam without self-production of electricity. In the TMP + Boiler case, a proper amount of biomass will be fed into for offering PM a certain amount of steam. In the case of TMP + BtSNG, more steam than normal supply from the BtSNG plant must be produced at the expense of bio-SNG yield.
As shown in Figure 8c,d, lower TMP SEC leads to higher economic profit in both NR and IRR. For NR, TMP + BIGCC > TMP + BtSNG > TMP + Boiler, but for IRR, TMP + BIGCC > TMP + Boiler > TMP + BtSNG. In the transport markets of Sweden where the natural gas price is relatively high and the feedstock supply is good, we are likely to see the first installation of commercial S&M scale bio-SNG production. However, since the biomethane market in Sweden is far from mature, it is still heavily dependent on political ambitions and associated instruments, as well as regional and local initiatives and a relatively high natural gas price.
Figure 8. Effect of reducing the TMP specific electricity consumption.
Figure 8. Effect of reducing the TMP specific electricity consumption.
Energies 08 12343 g008

4. Conclusions

A TMP + BtSNG mathematical model is developed based on the economic conditions in Sweden. The profitability of the TMP + BtSNG mill is evaluated in comparison with the TMP + BIGCC mill. The model prediction can be concluded as below:
The scale of the TMP + BtSNG mill and SNG price are two strong factors for the implementation of BtSNG in a TMP mill. A BtSNG plant associated to a TMP mill should be built at a scale above 100 MW of biomass thermal input.
Compared to the case of TMP + BIGCC, the NR and IRR of TMP + BtSNG are much lower. This is attributed to three reasons: (1) the specific investment cost is much higher for BtSNG; (2) The electricity certificate instrument in Sweden has added a credit to the electricity production; and (3) Much more DH is produced by BIGCC, which has an unusually high price (higher than electricity) in Sweden. Political instruments to support commercialization of transport biofuel are necessary. For countries where the heat price is lower, TMP + BtSNG will be more profitable.

Acknowledgments

The authors would like to acknowledge the project support of EU regional structure fund, Ångpanneföreningen Foundation for Research and Development, LKAB, Länsstyrelsen Västernorrland and Swedish Gasification Center (SFC).

Author Contributions

Wennan Zhang and Jie He developed and designed the process flow diagram as well as the physical and mathematical model. Per Engstrand and Olof Björkqvist provided information and data about biomass availability and process design in thermomechanical pulp mills. All authors participated the paper preparation and improvement.

Conflicts of Interest

The authors declare no conflict of interest.

Abbreviations

bdtbone dry ton
BIGCCbiomass integrated gasification combined cycle
bio-SNGSNG produced from biomass/biofuel
BtSNGbiomass to SNG
CHPcombined heat and power
CTMPchemithermomechanical pulp
dafdried and ash free
DDBdouble declining balance depreciation method
DFBGdual fluidized bed gasifier
DHdistrict heating
DIPdeinked pulp
FBfluidized bed
H&Pheat and power
HYPhigh-yield pulp
IRRinternal return rate
LHVlower heating value
NRnet revenue
PGWpressure groundwood
PMpaper mill
SECspecific electricity consumption
SECRreduction of SEC, %
SGWstone groundwood
SNGsynthetic natural gas
S&Msmall and medium
TMPthermomechanical pulp
tpyton per year
WHwaste heat

References

  1. Zhang, W. Automotive fuels from biomass via gasification. Fuel Process. Technol. 2010, 91, 866–876. [Google Scholar] [CrossRef]
  2. Dry, M.E. High quality diesel via the Fischer–Tropsch process—A review. J. Chem. Technol. Biotechnol. 2002, 77, 43–50. [Google Scholar] [CrossRef]
  3. Held, J. Small and Medium Scale Technologies for Bio-SNG Production; Svenskt Gastekniskt Center: Malmö, Sweden, 2013. [Google Scholar]
  4. Gassner, M.; Marechal, F. Thermo-economic optimisation of the polygeneration of synthetic natural gas (SNG), power and heat from lignocellulosic biomass by gasification and methanation. Energy Environ. Sci. 2012, 5, 5768–5789. [Google Scholar] [CrossRef]
  5. Engstrand, P.; Jonsson, J.; Sandberg, C.; Starck, G.; Wancke-Stahl, C.; Wahlgren, M. Method of Producing Bleached Thermomechanical Pulp (TMP) or Bleached Chemithermomechanical Pulp (CTMP). WO Patent WO/2003/000,982, 2003. [Google Scholar]
  6. Westermark, U.; Capretti, G. Influence of ray cells on the bleachability and properties of CTMP and kraft pulps. Nord. Pulp Paper Res. J. 1988, 3, 95–99. [Google Scholar] [CrossRef]
  7. He, J.; Engstrand, P.; Björkqvist, O.; Zhang, W. Techno-economic evaluation of a mechanical pulp mill with gasification. Nord. Pulp Paper Res. J. 2013, 28, 349–357. [Google Scholar] [CrossRef]
  8. Pettersson, J. Energy survey for energy management-Holmen Paper, Hallsta. Available online: http://epubl.ltu.se/1402-1617/2005/109/LTU-EX-05109-SE.pdf (accessed on 23 September 2012).
  9. Göransson, K.; Söderlind, U.; He, J.; Zhang, W. Review of syngas production via biomass DFBGs. Renew. Sustain. Energy Rev. 2011, 15, 482–492. [Google Scholar] [CrossRef]
  10. Phillips, S.; Aden, A. Thermochemical Ethanol via Indirect Gasification and Mixed Alcohol Synthesis of Lignocellulosic Biomass; National Renewable Energy Laboratory: Golden, CO, USA, 2007. [Google Scholar]
  11. Heyne, S. Bio-SNG from Thermal Gasification-Process Synthesis, Integration and Performance. Ph.D Thesis, Chalmers University of Technology, Göteborg, Sweden, 2013. [Google Scholar]
  12. Tunå, P. Substitute Natural Gas from Biomass Gasification; Svenskt Gastekniskt Center: Malmö, Sweden, 2008. [Google Scholar]
  13. Agersborg, J.; Lingehed, E. Integration of Power-to-Gas in Gasendal and GoBiGas. Master’s Thesis, Chalmers University of Technology, Göteborg, Sweden, 2013. [Google Scholar]
  14. Bader, A.; Bauersfeld, S.; Brunhuber, C.; Pardemann, R.; Meyer, B.; Siemens, A.G.; Solutions, E. Modelling of a chemical reactor for simulation of a methanisation plant. In Proceedings of the 8th International Modelica Conference, Dresden, Germany, 20–22 March 2011.
  15. He, J.; Göransson, K.; Söderlind, U.; Zhang, W. Simulation of biomass gasification in a dual fluidized bed gasifier. Biomass Convers. Biorefinery 2012, 2, 1–10. [Google Scholar] [CrossRef]
  16. He, J.; Zhang, W. Techno-economic evaluation of thermo-chemical biomass-to-ethanol. Appl. Energy 2011, 88, 1224–1232. [Google Scholar] [CrossRef]
  17. Porubova, J.; Bazbauers, G.; Markova, D. Modeling of the Adiabatic and Isothermal Methanation Process. Sci. J. Riga Tech. Univ. Environ. Clim. Technol. 2011, 6, 79–84. [Google Scholar] [CrossRef]
  18. Zwart, R.; Boerrigter, H.; Deurwaarder, E.P.; van der Meijden, C.M.; van Paasen, S.V.B. Production of Synthetic Natural Gas (SNG) from Biomass; Energy Research Centre of the Netherlands (ECN): Petten, The Netherlands, 2006. [Google Scholar]
  19. Thunman, H.; Alamia, A.; Berguerand, N.; Lind, F.; Seemann, M. Beyond 80% Efficiency for Standalone Production of Bio-Methane from Wet Biomass; Chalmers University of Technology: Göteborg, Sweden, 2014. [Google Scholar]
  20. Holmberg, J.M.; Gustavsson, L. Systems aspects on new energy technologies in the pulp and paper industry. In Proceedings of the 3rd International Green Energy Conference IGEC-III, Västerås, Sweden, 18–20 June 2007.
  21. Wetterlund, E.; Söderström, M. Biomass gasification in district heating systems—The effect of economic energy policies. Appl. Energy 2010, 87, 2914–2922. [Google Scholar] [CrossRef]
  22. Eriksson, G.; Kjellström, B. Assessment of combined heat and power (CHP) integrated with wood-based ethanol production. Appl. Energy 2010, 87, 3632–3641. [Google Scholar] [CrossRef]
  23. He, J.; Engstrand, P.; Björkqvist, O.; Zhang, W. Bio-SNG production in a TMP mill in comparison with BIGCC. Energy Procedia 2014, 61, 2894–2897. [Google Scholar] [CrossRef]

Share and Cite

MDPI and ACS Style

Zhang, W.; He, J.; Engstrand, P.; Björkqvist , O. Economic Evaluation on Bio-Synthetic Natural Gas Production Integrated in a Thermomechanical Pulp Mill. Energies 2015, 8, 12795-12809. https://doi.org/10.3390/en81112343

AMA Style

Zhang W, He J, Engstrand P, Björkqvist  O. Economic Evaluation on Bio-Synthetic Natural Gas Production Integrated in a Thermomechanical Pulp Mill. Energies. 2015; 8(11):12795-12809. https://doi.org/10.3390/en81112343